Change Order Invoice: How to Bill Approved Changes Correctly

A change order invoice is the bill you send a client for an approved, signed change order, separate from or clearly itemized within your regular draw. It should reference the change order number, describe the change in one line, show the approved amount, list any payment already received, and state the payment terms from your contract. Bill each change when your terms say to, usually at signing or on the next draw, not in a pile at the end.

Billing change orders late is one of the most common ways builders lose money they already earned. By the final draw, the client is tired, the budget is stretched, and every change order gets relitigated. A clean invoice sent on time turns a signed change into collected cash while everyone still remembers why it happened.

What should a change order invoice include?

Here’s the checklist. If any of these are missing, expect a question.

  • Invoice number and date.

  • Project address and client names.

  • Change order number. Matching the signed change order.

  • Short description. One line, matching the change order description.

  • Approved amount. Exactly as signed. Credits shown as negatives.

  • Amount previously billed or paid. If billing in parts.

  • Amount due now.

  • Payment terms and due date. From your contract.

  • Revised contract total. Original contract plus all approved changes to date.

  • Copy of the signed change order attached.

When should you bill change orders?

When your contract says to. The two common approaches are billing at signing, before the work starts, or adding approved changes to the next draw. Many custom builders collect at signing, or at least a deposit, especially on larger changes or anything with special-order materials.

What I wouldn’t do is wait. Billing change orders at the end puts all the risk on you. Put your terms in the contract and on every change order form. For more on setting those terms, see change order policies.

How to invoice a change order, step by step

  1. Confirm it’s signed. No signature, no invoice.

  2. Check your payment terms. At signing, at start, at completion, or next draw.

  3. Create the invoice. Reference the change order number and match the amount exactly.

  4. Attach the signed change order. So the client doesn’t have to find it.

  5. Update the revised contract total. On the invoice and in your records.

  6. Send it the same day it’s due. Not at the end of the month.

  7. Record payment. In your accounting and your change order log.

  8. Follow up on late payments. Per the contract, before more work proceeds if your terms allow.

If you want the change order side of this already set up, our Custom Home Change Order Template is a template plus a guide for a simple, profitable change order system, with payment terms right on the form.

Change orders on draw requests: how do they work?

If your project has a construction loan, change orders on draw requests usually show up as added lines in the schedule of values or budget, with the approved amount and percent complete. The lender may need to approve the change before funding it, and some changes may need to be paid by the client directly if the loan doesn’t cover them.

  • Add a line for each approved change. Don’t merge changes into existing lines.

  • Bill by percent complete or in full, depending on your terms and the lender’s.

  • Keep client-paid changes separate from lender-funded ones.

  • Attach signed change orders to the draw package.

Lender requirements vary, so ask yours how they want changes shown. See construction draw requests and schedules of values.

Change order invoice example

Hypothetical, filled in:

  • Invoice: #1047, dated 6/3

  • Project: 123 Oak Lane

  • For: Change Order #7, add two island outlets

  • Approved amount: $450

  • Previously paid: $0

  • Amount due: $450, due upon receipt per contract change order terms

  • Original contract: $750,000

  • Approved changes to date (CO #1 through #7): $18,450

  • Revised contract total: $768,450

Showing the running total does two things. It keeps the client aware of where they stand, and it prevents the end-of-job surprise that leads to disputes.

What change order payment terms should you use?

Pick terms that keep you from financing the client’s changes. Common change order payment terms include:

  • Paid in full at signing. Simple and safe for smaller changes.

  • Deposit at signing, balance at completion. For larger changes.

  • Added to next draw. Common on loan-funded projects.

  • Materials paid up front. For special-order or non-returnable items.

Whatever you choose, put it in the contract, on the change order, and on the invoice. Consistency is what makes it enforceable in practice. Ask your attorney to review the contract language.

Common change order billing mistakes

  • Billing at the end. The most expensive mistake on this list.

  • Amounts that don’t match the signed form. Every mismatch invites a dispute.

  • Mixing changes into base contract lines. Nobody can tell what was what.

  • Forgetting credits. Clients remember credits. Show them.

  • No running total. Clients lose track and feel ambushed.

A change order invoice is the last step of a process that starts with a clear change order. A consistent Custom Home Change Order Template keeps the number, amount, and terms identical from signature to payment.

Frequently asked questions

Should change orders be invoiced separately from draws?

Either works, as long as they’re itemized and match the signed change orders. Separate invoices are often clearer for client-paid changes.

Can I stop work if a change order invoice isn’t paid?

It depends on your contract and state law. Many contracts allow suspending the changed work until payment, so check yours with your attorney.

How do I invoice a credit change order?

Show it as a negative amount referencing the change order, and apply it to the contract total or the next draw.

Do I charge sales tax on change orders?

That depends on your state and how your contract is structured. Ask your CPA.

BTW, if you want every approved change to carry clear payment terms from the start, grab our Custom Home Change Order Template over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.

Previous
Previous

Change Orders and Your Construction Loan: Who Pays and How

Next
Next

Types of Change Orders in Construction: With Examples