Types of Change Orders in Construction: With Examples

The main change order types in residential construction are owner requested changes, field change orders for unforeseen conditions, design error or omission changes, code or regulatory changes, allowance overages, deductive changes (credits), and builder-initiated substitutions. Each type has a different cause, a different person responsible for the cost, and a different paper trail. Knowing which one you’re dealing with tells you who pays and how to document it.

When every change gets treated the same, the wrong person ends up paying. Builders eat costs that belonged to the client, or bill clients for things that were their own mistakes and lose trust doing it. Sorting by type is how you stop both.

What are the types of change orders in construction?

Here are the common types of change orders in construction, in plain terms:

  • Owner requested. The client wants something added, removed, or different.

  • Field change order. Something discovered on site changes the work: rock, rot, utility conflicts.

  • Design error or omission. The plans are wrong, conflicting, or missing something.

  • Code or regulatory. An inspector or jurisdiction requires something the plans didn’t show.

  • Allowance overage. A selection costs more than the allowance in the contract.

  • Deductive. Work removed, resulting in a credit.

  • Builder substitution. The builder proposes a different product or method, often due to availability.

  • Zero-cost. A documented change with no price impact.

Some contracts also use a change directive, where work proceeds before the price is agreed. That’s its own tool. See change order vs change directive.

What is an owner requested change order?

An owner requested change order is the most common type on a custom home. The client changes their mind, adds a feature, or upgrades a finish. The client pays for the work, your markup per contract, and any schedule impact.

Example: client adds a second dishwasher. Cabinet change, plumbing, electrical, appliance. Priced, signed, paid, built. These are the easiest to justify because the request is the reason.

What is a field change order?

A field change order covers a condition found during construction that the plans and contract didn’t anticipate. Who pays depends on your contract. Many residential contracts put unforeseen subsurface or concealed conditions on the owner, but the language varies, and your attorney should review it.

Field changes need fast documentation because the evidence gets covered up. Photos, the trade’s written description, and a notice to the client before work continues, if your contract requires it. For how to build that record, see change order justification.

How to identify the change order type, step by step

  1. Ask who started it. The client, the field, the design, the inspector, or you.

  2. Check the plans and specs. Was it shown, specified, or excluded?

  3. Check the contract. Allowances, unforeseen conditions, and exclusions.

  4. Assign the type. One primary type per change order.

  5. Decide who pays. Based on type and contract.

  6. Document accordingly. Each type needs different backup.

  7. Log it by type. So you can see patterns later.

Sorting types is easier when every change goes on the same form. Our Custom Home Change Order Template is a template plus a guide for a simple, profitable change order system.

Change order types with examples

A sample set from a hypothetical custom home, round numbers:

  • CO #3, owner requested: add built-in bench in mudroom. $2,200, 1 day. Client pays.

  • CO #5, field change: rotted sill plate found at existing garage tie-in. $1,400, 1 day. Per contract, client pays.

  • CO #6, design omission: beam size missing on plans, engineer specifies a larger beam. $900, 0 days. Depends on contract and who provided the plans.

  • CO #8, code: inspector requires added guardrail at a window. $350, 0 days. Usually client pays unless the builder missed a known requirement.

  • CO #10, allowance overage: lighting fixtures over allowance. $3,100 plus markup per contract, 0 days. Client pays.

  • CO #11, deductive: client deletes outdoor kitchen. Credit of $6,500, 0 days. See deductive change orders.

  • CO #12, builder correction: wrong tile layout corrected. $0 to client, documented.

Who pays for each type of change order?

It depends on the contract, but here’s the general pattern most builders follow:

  • Owner requested: client.

  • Allowance overage: client.

  • Field and unforeseen conditions: usually client if the contract says so.

  • Code changes: often client, unless it was a requirement the builder should have known.

  • Design errors: whoever is responsible for the design. On design-build, that may be you.

  • Builder mistakes: builder.

If the contract doesn’t say, you’re negotiating after the fact, which is the worst time. Put it in the change order clause. See change order clauses in construction contracts.

Why track change order types?

Because the pattern tells you what to fix. If most of your changes are owner requested, your selections process may need work. If they’re design omissions, your plan review needs work. If they’re field changes, maybe your site investigation does. A log sorted by type is the cheapest consultant you’ll ever hire.

Change order types only help if you record them consistently. A standard Custom Home Change Order Template keeps the type, reason, price, and days on every change, so your log becomes something you can learn from. Track them in a change order log.

Frequently asked questions

What is the most common type of change order?

On custom homes, owner requested changes are usually the most common, followed by allowance overages.

Is a field change order the same as a change directive?

Not exactly. A field change order documents a field condition. A change directive authorizes work before the price is agreed, and some field changes use one.

Do zero-cost changes need a change order?

Yes. Any deviation from the plans or specs should be documented, even when no money changes hands.

Can one change order cover more than one type?

It can, but it’s cleaner to split them. One type per change order makes the responsibility and the backup clear.

BTW, if you want every type of change on the same clear form, grab our Custom Home Change Order Template over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.