A construction draw request is the package a builder submits to a construction lender, or to a client paying directly, asking to be paid for work completed during a period. To prepare one that gets paid, tie each requested amount to a budget line, show percent complete against the approved budget, attach the backup the lender requires, and make sure the work is actually in place when the inspector shows up. Lenders pay clean, verifiable requests. They slow down everything else.
Cash flow problems in home building are often draw problems. The work is done, but the money sits for two extra weeks because the request didn’t match the budget, a lien waiver was missing, or the inspector found less work than the request claimed. All fixable before you hit send.
What is the draw request process?
The draw request process on a typical construction loan looks like this. Each lender has its own forms and rules, so read your loan documents.
Update your budget. Record costs and percent complete by line.
Prepare the request. Lender’s form or your own, showing amounts by budget line.
Attach backup. Invoices, lien waivers, change orders, and whatever else the lender requires.
Submit on the lender’s schedule.
Inspection. The lender sends an inspector to verify the work in place.
Review and approval. The lender compares the request to the inspection and the budget.
Funding. Money is released, sometimes minus a holdback or retainage.
Pay your trades per your payment terms.
What should a draw request form include?
A draw request form, whether it’s the lender’s or yours, usually needs:
Project information. Borrower, address, loan number, draw number, and period.
Budget by line. Original budget, approved changes, and revised budget for each line.
Previously drawn. What’s already been funded on each line.
This request. The amount requested on each line this period.
Percent complete. For each line and for the project.
Balance to finish. What remains on each line.
Change orders. Any approved changes affecting the budget.
Certification and signature. Usually the borrower and the builder.
The single most common reason requests get kicked back is a mismatch between the request and the lender’s approved budget. Use their line items, or keep a crosswalk from your budget to theirs. Our Construction Budget and Specifications Template gives you the budget structure the request draws from.
How does a construction loan draw inspection work?
A construction loan draw inspection is a site visit where the lender’s inspector verifies that the work you’re requesting payment for is actually in place. They typically walk the house, compare progress to your request, take photos, and report a percent complete to the lender.
How to make inspections go smoothly:
Request what’s in place, not what’s scheduled. If drywall starts Monday, don’t bill drywall on Friday.
Make the site accessible. Lockbox code, gate code, a clear path.
Know what they count. Some lenders don’t pay for materials stored on site until installed. Ask.
Be available. If the inspector has a question, a quick answer avoids a reduced draw.
Review the inspection report. If the inspector missed something, ask the lender how to address it.
How do you prepare a construction draw request that gets paid fast?
Here’s my checklist for a clean construction draw request:
Match the lender’s budget lines. Same names, same order.
Bill honestly. Percent complete you could defend standing in the house.
Include every required document. Missing paperwork is the top cause of delay.
Collect lien waivers from trades for prior payments, if the lender requires them. Rules and forms vary by state. See conditional vs. unconditional lien waivers.
Include approved change orders that changed the budget.
Check the math. Totals, previous draws, and remaining balances.
Submit on time. Many lenders have a monthly cutoff. Miss it and you wait.
What does a draw request look like in practice?
Say a $500,000 construction budget, hypothetical numbers. At the end of framing, your request might show foundation at 100 percent, framing at 100 percent, roofing at 50 percent, and windows at 100 percent if installed. Every other line is at zero or close to it. The total requested is the sum of the newly completed work on each line, less anything the lender holds back.
The inspector walks the house, sees the slab, the frame, half the roof, and the windows set, and reports roughly the same. Clean match, fast funding. If the request had billed the whole roof and the inspector found half, expect a reduced draw and a delay.
How do draws connect to your budget and trades?
Draws are only as good as your budget. If your budget is out of date, your draw request will be a guess. Update the budget weekly, and the draw becomes a summary of what you already know. See construction budget template.
Coordinate trade payments with your draw timing so trades know when to expect money. And when clients pay directly rather than through a lender, the same discipline applies. See construction draw schedule and spec home financing.
Frequently asked questions
How often can I submit a construction draw request?
Many lenders allow one draw per month, some more often. It depends on your loan, so check your loan agreement.
Why was my draw request reduced?
Usually because the inspector found less work in place than requested, or paperwork was missing. Ask the lender for the reason and fix it on the next request.
Do lenders pay for stored materials?
Some do with conditions, many don’t. Ask your lender before you order expensive materials early.
What documents are usually needed for a draw?
Commonly the draw form, invoices, lien waivers, and any approved change orders. Each lender sets its own list.
BTW, if you want a budget your draw requests can pull straight from, grab our Construction Budget and Specifications Template over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.