A construction schedule of values template is a table that breaks the total contract price into line items of work, each with a dollar value, so progress payments can be calculated by percent complete. Each line shows the scheduled value, work completed in prior periods, work completed this period, materials stored, total completed to date, percent complete, balance to finish, and retainage if it applies. The lines must add up exactly to the contract sum.
Get the schedule of values wrong and every draw turns into a negotiation. Front-load it too obviously and the lender or owner pushes back. Build it too thin and you end up financing the job yourself for months. It’s a one-page document that controls your cash flow for the whole project.
What is a construction schedule of values?
A construction schedule of values is the agreed breakdown of the contract price by scope. It becomes the basis for every payment application. When you bill, you report how far along each line is, and the payment is calculated from those percentages.
On commercial work it’s standard. On residential jobs, it shows up most often when there’s a construction lender, a cost plus contract with progress billing, or an owner who wants payments tied to measurable progress. Some lenders use their own fixed draw schedule instead, which I cover in construction draw schedules.
What columns go in a construction schedule of values template?
Here’s the standard column checklist:
Item number. Matches your budget or cost codes.
Description of work. Clear enough that an inspector can verify it.
Scheduled value. The dollar amount assigned to that line.
Work completed, previous periods. Carried from the last application.
Work completed, this period. New progress.
Materials presently stored. If your contract and lender allow billing for stored materials.
Total completed and stored to date. The sum of the last three.
Percent complete. Total to date divided by scheduled value.
Balance to finish. Scheduled value minus total to date.
Retainage. If the contract holds it back. See retainage in construction.
How to create a schedule of values, step by step
Build it from your budget, not from scratch. Here’s the process I’d follow:
Start with your line-item budget. Every cost is already there. See construction budget line items.
Group lines into billable items. Combine small lines so there are enough items to show progress but not so many that billing is tedious.
Allocate fee and overhead. Spread them across lines in proportion to cost, or show them as their own line if the contract allows.
Allocate general conditions. As a separate line billed over time, or spread across the work.
Check the total. It must equal the contract sum to the dollar.
Sanity-check for front-loading. Early items shouldn’t be priced well above their real cost.
Get it approved. Owner, architect, or lender signs off before the first payment application.
Update with change orders. Add each approved change as a new line.
A clean line-item budget makes this easy. The Construction Budget and Specifications Template gives you detailed budget and specifications templates in a simple system you can roll up into a schedule of values.
Schedule of values example
Here’s a simplified schedule of values example for a hypothetical $600,000 home, at the second payment application. Round numbers, for format only:
1. General conditions: $36,000 scheduled. $9,000 to date. 25 percent.
2. Site work and foundation: $54,000 scheduled. $54,000 to date. 100 percent.
3. Framing and sheathing: $90,000 scheduled. $45,000 to date. 50 percent.
4. Roofing: $30,000 scheduled. $0 to date. 0 percent.
5. Windows and exterior doors: $42,000 scheduled. $21,000 stored on site. 50 percent.
6 through 15. Remaining trades: $348,000 scheduled. $0 to date.
Total: $600,000 scheduled. $129,000 completed and stored. 21.5 percent complete. Balance to finish $471,000.
Retainage at 10 percent, if required: $12,900 held. Amount earned less retainage: $116,100.
Subtract what was already paid on the first application, and that’s the current payment due.
How is a schedule of values used for draws?
When you use a schedule of values for draws, each payment application reports progress line by line, and the lender’s inspector or the owner’s representative checks it against the site. If they agree framing is 50 percent done, you get paid for 50 percent of the framing line, less retainage.
Bill what you can prove. Photos and inspection reports help.
Match your draw request. The totals should tie exactly. See construction draw requests.
Track stored materials carefully. Many lenders want invoices and proof they’re on site or insured.
Keep change orders separate. New lines, not edits to old ones.
What is front-loading a schedule of values?
Front-loading means assigning more value to early items than they actually cost, so you collect more cash up front. Some builders do it a little to cover mobilization and deposits. Overdo it and you lose credibility with the lender, and if the job goes sideways, the remaining money may not cover the remaining work.
My rule is simple: price each line close to its real cost plus a fair share of fee. If an inspector would raise an eyebrow at a line, fix it before you submit.
What are common schedule of values mistakes?
Totals that don’t match the contract. Even by a few dollars.
Too few lines. “Framing through drywall” can’t be measured.
Too many lines. Two hundred items makes every billing a chore.
Burying general conditions. Then you can’t bill for time on site.
Editing original lines for changes. Always add new lines.
No link to the budget. You can’t compare billed vs spent.
The fix for most of these is a well-built budget underneath. Construction budget and specifications covers that foundation, and the Construction Budget and Specifications Template keeps the budget and specs organized in one system so your construction schedule of values template has something solid to pull from.
Frequently asked questions
Who prepares the schedule of values?
The contractor prepares it, and the owner, architect, or lender reviews and approves it before the first payment application.
Can a schedule of values be changed after approval?
Usually only by approved change orders or by mutual agreement. Reallocating between lines typically needs the reviewer’s sign-off.
Does a residential lender require a schedule of values?
Some do, some use their own draw schedule. Requirements vary by lender, so ask before you set up your billing.
Is the schedule of values the same as the budget?
No. The budget shows your cost. The schedule of values shows the contract price allocated to scope for billing.
BTW, if you want a line-item budget that rolls cleanly into a schedule of values, grab our Construction Budget and Specifications Template over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.