How to Write a Change Order Policy for Your Clients

A change order policy is a short written document that tells clients how changes work on their build: how to request one, how it’s priced, what fees apply, when it needs to be approved and paid, how it affects the schedule, and when changes are no longer accepted. Write it in plain language, give it to clients before they sign the contract, and make sure it matches the change order clause in your contract.

The contract clause is for the attorney. The policy is for the client. Most clients won’t read paragraph 14 of your agreement. They will read a one-page document that explains the rules in normal words. And clients who know the rules up front rarely fight about them later.

What should a change order policy include?

A change order policy should answer every question a client will ask about changes, before they ask. Here are the sections I’d include:

  1. What counts as a change. Anything different from the signed plans, specs, and selections, including additions, deletions, and substitutions.

  2. How to request one. In writing, to a named person. Not to the framer on a Saturday.

  3. How changes are priced. Cost plus your standard markup, and how credits are handled.

  4. Fees. Any administrative fee per change order.

  5. Approval. No work until the change order is signed.

  6. Payment. When change orders are paid, ideally up front or with the next draw.

  7. Schedule. Changes may add time, and the change order will say how much.

  8. Cutoffs. Points in the build after which certain changes aren’t accepted, or cost more.

  9. Zero-cost changes. They still get documented.

How should you handle change order fees?

Change order fees cover the real work every change creates: getting bids, revising drawings, updating the schedule, calling trades, and processing paperwork. Many builders charge a flat administrative fee per change order for that reason. Others build it into the markup. Either way, state it clearly in the policy and the contract.

Some approaches I’ve seen work:

  • A flat fee per change order, charged even on small changes.

  • A higher fee for late changes, after a defined phase like drywall.

  • No fee on credits, but no full markup credit either.

  • Fees waived for builder-caused changes, which is only fair.

Whatever you pick, apply it every time. Inconsistency is what makes clients feel nickeled and dimed. More on pricing in change order markup.

What is a good change order process for clients?

A good change order process for clients is simple enough to fit on one page. Something like:

  1. Send your request in writing to your project manager.

  2. We’ll price it within a stated number of business days, including any schedule impact.

  3. You review and decide by a stated deadline so the job doesn’t stall.

  4. Sign and pay per the policy before work begins.

  5. We update the log and send you the new contract total.

That process mirrors what I lay out in how to write a construction change order, just written for the client’s side of the table.

What does a client change policy look like in practice?

Here’s a short sample client change policy, written in the client’s language. Adjust it to your contract and have your attorney review it.

  • Changes happen. We expect them and have a process to handle them.

  • Every change is written. If it isn’t on a signed change order, it isn’t approved.

  • You’ll see the price first. Including cost, our markup, any fee, and any added days.

  • Changes are paid when approved. So there are no surprises at the end.

  • Some changes get harder over time. Moving a wall is easy on paper, harder after framing, and expensive after drywall.

  • After a set point, we stop accepting certain changes so we can finish your home on schedule.

  • We’ll send you an updated change order log regularly.

Our Custom Home Change Order Template gives you the form and the guide for the process behind a policy like this.

Where does the policy fit with the rest of your client documents?

It belongs in the stack you hand clients before they sign. Alongside it, I’d want a clear contract clause, a client contingency explanation, and a pre-construction meeting where you walk through all of it. See change order clause and four client policies for smoother builds.

The policy and the contract must say the same thing. If they conflict, the contract usually controls, and you’ll lose credibility pointing to a policy that doesn’t match it.

How do you enforce a change order policy?

By following it yourself. The first time you “just take care of it” in the field, you’ve told the client the policy is optional. A few habits keep it real:

  • Train your field team. Superintendents and trades send change requests to the office, not to a tape measure.

  • No signature, no work. Every time.

  • Bill on schedule. If the policy says changes are paid at approval, collect at approval.

  • Keep the log current and share it. See change order log.

Frequently asked questions

Should I charge a fee for every change order?

Many builders charge a flat administrative fee because every change takes real time. Whatever you choose, state it in writing and apply it consistently.

When should clients get the change order policy?

Before the contract is signed, ideally walked through in a meeting. Clients accept rules they knew about from the start.

Can I refuse a change late in the build?

If your contract and policy set cutoffs, yes. Put the cutoffs in writing and have your attorney review them.

Does the policy replace the contract clause?

No. The clause is the legal term. The policy explains it in plain language. They should match.

BTW, if you want the form and the process behind your change order policy ready to go, grab our Custom Home Change Order Template over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.