Change Orders and Your Construction Loan: Who Pays and How

Change orders on a construction loan are usually paid one of two ways: out of your own pocket, or through the loan if your lender approves the change and there’s room in the budget or contingency. Most construction lenders lend against a fixed budget and appraisal, so when you add something that costs more, the lender may want to approve it, may require you to pay the difference in cash, or both. Ask your lender how they handle changes before construction starts.

This catches a lot of homeowners off guard. You sign a change order with your builder, assume the bank will cover it like everything else, and then the next draw comes back short. Now the builder is waiting on money, the work slows down, and you’re scrambling for cash you didn’t plan to spend.

How do change orders work with a construction loan?

Your construction loan was approved for a specific budget, and the appraisal was based on specific plans. A change order changes one or both. The lender wants to make sure the loan is still covered by the value of the finished house and that there’s enough money left to finish it.

So when you approve a change, a few things can happen:

  • It fits in the contingency. Some lenders let you use a contingency line for changes, with approval.

  • It’s offset by a credit. If you deleted something else, the savings may cover it.

  • You pay the difference. Many lenders require cash for changes that increase the budget.

  • The lender re-reviews. Larger changes may need a revised budget or even a new appraisal.

Every lender is different, so treat this as a list of questions, not answers. For the loan basics, see construction loans for building on your own land.

Do change orders need lender approval?

Often, yes. Change orders and lender approval go together on many construction loans, especially changes over a certain size or anything structural. Your loan documents will say what requires approval. Some lenders want to see every change. Others care only when the total budget moves.

Ask your lender these before the build starts:

  • Which changes need your approval?

  • Can changes be paid from the contingency?

  • Do I have to pay increases in cash?

  • When do you need the cash, before the work or at the next draw?

  • Will a large change require a new appraisal?

  • How do credits get applied?

How to handle a change order with a construction loan, step by step

  1. Ask your builder for a price first. In writing, with the schedule impact.

  2. Check with your lender. Does it need approval, and how will it be paid?

  3. Decide how you’ll pay. Contingency, cash, or a credit elsewhere.

  4. Sign the change order. Only after you know how it’s being paid.

  5. Send the signed change order to your lender if they require it.

  6. Pay your share on time. Per your builder’s change order terms.

  7. Keep a running total. Every change, its amount, and how it was paid.

Builders who run a clear change order system make this a lot easier on you. The Custom Home Change Order Template is the template and guide many builders use, and it’s a useful reference for what a complete change order should look like.

Paying for change orders out of pocket: what to expect

Paying for change orders out of pocket is common, even when you have a construction loan. Many builders ask for payment at signing or at the next draw, and many lenders won’t increase the loan mid-build.

Plan for it. A lot of homeowners set aside a cash cushion beyond their down payment for exactly this. How much depends on your plans, your lender, and how sure you are about your selections. Our guide on how to budget for building a house covers building that cushion in.

Example: a construction loan change order

Hypothetical, round numbers:

  • Loan budget: $600,000, with a $20,000 contingency

  • Change: you upgrade the kitchen countertops and add a pantry door

  • Change order total: $8,000

  • Lender’s rule (in this example): changes over $5,000 need approval, and owner upgrades are paid in cash

  • Result: lender approves the change, you pay $8,000 to the builder per the change order terms, contingency stays intact

If you had assumed the loan would cover it, the builder would have been short $8,000 at the next draw. That’s the conversation you want to have before you sign, not after.

What happens to credits on a construction loan?

When you remove something, you get a credit, called a deductive change order. Depending on the lender, the credit may reduce the loan amount, stay in the budget for other changes, or be applied to the contingency. Ask how your lender treats credits. See change orders for homeowners for how credits and additions usually work with your builder.

Mistakes homeowners make with change orders and loans

  • Assuming the loan pays for everything. It might not.

  • Signing before asking the lender. Then finding out it needs approval.

  • Using up the contingency on upgrades. Then having nothing left for real surprises.

  • Not tracking the total. Small changes add up fast.

  • Waiting to pay. It can slow your builder and your schedule.

Change orders on a construction loan go smoothly when everyone sees the same paperwork. If your builder uses a system like the Custom Home Change Order Template, every change will show the price, schedule impact, and payment terms, which is exactly what your lender needs to see too. To make fewer changes in the first place, try the home construction checklist for homeowners.

Frequently asked questions

Can I increase my construction loan for change orders?

Some lenders allow a loan modification, but many don’t mid-build. Ask your lender early, and plan for cash.

Can the contingency be used for upgrades?

Sometimes, with lender approval. Many homeowners save it for unforeseen issues instead of upgrades.

Will a change order affect my appraisal?

Small changes usually don’t. Large changes that alter the size or design may require the lender to update the appraisal.

Who tells the lender about a change order?

Usually the builder submits it with the draw, but you’re the borrower. Confirm with both your builder and lender who handles it.

BTW, if you want to see what a complete, lender-friendly change order should look like, grab our Custom Home Change Order Template over at the Building Optimal Shop. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.

Previous
Previous

Verbal Change Orders: Why They Cause Fights and How to Avoid Them

Next
Next

Change Order Invoice: How to Bill Approved Changes Correctly