Retainage in construction is a portion of each payment that’s held back until the work is complete, as security that the contractor or subcontractor will finish and fix punch items. On a home build, a client or lender may hold retainage from the builder, and the builder may hold retainage from trades. The percentage, release timing, and any limits are set by contract and, in some places, by state law, so confirm the rules with your attorney.
Retainage is one of those things that sounds simple and creates a lot of uncomfortable phone calls at the end of a job. Used well, it keeps everybody motivated to finish. Used carelessly, it starves your trades and makes the last 5 percent of the house take forever.
What is retainage in construction?
It’s money earned but not yet paid. Say a trade invoices $20,000 for completed work and the contract calls for 10 percent retainage. You pay $18,000 now and hold $2,000. Over the job, those holds add up, and the total gets released when the trade’s work is complete and accepted.
You’ll also hear it called retention. Construction retainage, retention, and retainage all mean the same thing in practice.
How does construction retainage work on a home build?
On residential projects, construction retainage typically flows like this:
The contract sets the terms. The percentage held, when it’s released, and what has to be true before release.
Each payment is reduced. Retainage is held from each progress payment or draw.
The held amounts are tracked. By trade, by job, so nobody loses count.
Completion triggers release. Usually substantial completion, a punch list sign-off, final inspection, or a defined period after.
Release comes with paperwork. Often a final invoice and lien waivers, depending on your state and contract.
Some builders hold retainage on every trade. Many residential builders hold it only on certain trades, or not at all, and rely on the final payment as the incentive instead. Either can work. What matters is that it’s in writing and applied consistently.
Should builders hold retention from subcontractors?
It depends on the trade and your market. Retention in construction makes the most sense for trades whose work has a long tail of punch items or warranty risk. It makes less sense on small trades with a single short visit.
Some things to weigh:
Trade cash flow. Many residential trades run thin. Holding a big percentage can push good trades away or get your bids padded.
Your client’s terms. If your client or lender holds retainage from you, you may want matching terms with trades so you aren’t financing their retainage yourself.
The final payment already works. For many trades, the last invoice for punch-out is leverage enough.
Local practice and law. Some states limit retainage percentages or set release deadlines. Ask your attorney.
How does retainage release work?
Retainage release should follow a clear, written standard so it’s not a negotiation at the end. Here’s a simple checklist:
Work complete. The trade’s full scope is finished.
Punch items corrected. Your punch list for that trade is signed off. See punch list.
Inspections passed. Any required final inspections for their work.
Paperwork in. Final invoice, any warranty documentation, and the lien waivers your contract requires. See lien waiver.
Release timing. Pay within the period your contract states, or that state law requires if it applies.
Then release it. Sitting on retainage after a trade has earned it hurts your reputation more than almost anything else you can do with money.
How should you track retainage?
Track it by trade and by job, separate from regular payables. If retainage lives in someone’s head, it gets forgotten in both directions: trades don’t get paid, or you pay twice.
A tracking sheet with these columns works fine:
Job and trade.
Contract amount and retainage percentage.
Retainage held to date.
Release conditions met and the date met.
Amount released and the date paid.
Retainage also affects your job budget and cash flow forecast. Money you’re holding still belongs in your committed costs. More on that in construction draw schedule.
How do you explain retainage to trades?
Up front, before the first invoice. If a trade learns about your retainage policy when their first check comes in short, you’ve started the relationship with an argument.
Put the terms in your subcontractor agreement and repeat them in plain language when you onboard the trade. Our Subcontractor Paperwork Package includes an onboarding letter where payment terms like this belong. If you also use payment clauses tied to client payments, see pay-when-paid vs. pay-if-paid.
Frequently asked questions
What is a typical retainage percentage?
It varies by contract, project type, and state. Some states cap it. Ask your attorney what’s common and allowed where you build.
When should retainage be released?
When the conditions in the contract are met, typically completion, punch sign-off, and paperwork. Some states set deadlines for release.
Is retainage common on residential projects?
It’s more common on commercial work. Many residential builders use it selectively or rely on the final payment instead.
Can a lender hold retainage from a builder?
Some construction lenders hold back a portion of draws until completion. Read your loan documents and ask your lender how they handle it.
BTW, if you want retainage terms explained to every trade before the first invoice, grab our Subcontractor Paperwork Package over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.