A kitchen selections checklist for a new home runs in this order: layout and appliances first, then cabinets, then plumbing fixtures and sinks, then countertops, then backsplash tile, lighting, and hardware, with paint and small details last. The order matters because each decision sets the dimensions or the look of the next one. Make them out of order and you’ll end up redoing work, paying for it, or both.
The kitchen is the most expensive room per square foot in most houses, and it’s where most of the hard decisions live. It’s also where homeowners lose the most time. A clear list, in the right order, with dates next to it, takes most of the stress out.
Why does the order of kitchen selections matter?
Because the kitchen is a chain of dependencies. The appliances set the cabinet openings. The cabinets set the countertop template. The sink sets the cabinet base and the plumbing rough-in. The countertop sets where the backsplash starts and stops. If you pick a range after the cabinets are built, you may be buying a new cabinet.
The other reason is lead time. Some kitchen items take weeks or months to arrive, and your builder needs the decision early enough to order them. Ask your builder for a selections schedule and work backward from it. If you want the bigger picture across the whole house, the custom home selections checklist covers every room.
The kitchen selections checklist, in order
Here’s the kitchen selections checklist I’d hand any homeowner. Work it top to bottom.
Layout and function. Confirm the island size, walkway widths, where the trash and recycling go, and whether you want a walk-in or cabinet pantry.
Appliances. Range or cooktop and wall ovens, refrigerator, dishwasher, microwave, hood, and any extras like a beverage fridge. Get the exact model numbers. More on this in appliance selections for new construction.
Cabinets. Door style, wood species or material, finish color, interior accessories, and crown or trim details.
Sink and faucet. Undermount or farmhouse, single or double bowl, faucet style and finish, pot filler, disposal, and any filtered water tap.
Countertops. Material, color, edge profile, and thickness. Approve the slab and the seam locations before fabrication.
Backsplash. Tile, height (to the underside of the uppers or full height), grout color, and where it ends on open walls.
Lighting. Recessed cans, pendants over the island, under-cabinet lights, and switch locations.
Hardware. Knobs and pulls, sizes, and finish. Make sure the finish works with the faucet.
Outlets and small details. Island outlets, appliance garages, charging spots, and paint color for any painted surfaces.
What new construction kitchen selections are due first?
The appliances and the cabinet layout are due first, usually before or right around framing. Those are the new construction kitchen selections that drive the plumbing, gas, and electrical rough-in, and the rough-in happens long before anything pretty shows up.
Here’s what typically needs to be final by the rough-in stage:
Gas or electric cooking. This changes what gets run to the range location.
Hood type and venting. A wall hood, island hood, and downdraft all vent differently.
Refrigerator water line. And whether it’s built-in, panel-ready, or freestanding.
Sink and dishwasher location. Plumbing rough-in depends on it.
Pendant and can locations. The electrician sets boxes before drywall.
Anything you change after rough-in usually means opening walls, so it costs more than it would have earlier.
How do you make kitchen finish selections without regret?
Pick one or two anchor pieces and build the rest around them. For most people the anchor is the countertop or the cabinet color. Once that’s chosen, kitchen finish selections like backsplash, hardware, and paint get a lot easier because you’re choosing what works with the anchor, not choosing from the whole world.
A few habits help:
See samples together. Put the cabinet door, the countertop sample, and the tile on the same table in daylight.
Check finishes against each other. Faucet, hardware, and lighting finishes don’t have to match, but they should look intentional.
Think about cleaning. Glossy dark surfaces and textured tile both show more than you’d think.
Decide once. Second-guessing after the order is placed is where change orders come from. Our guide to change orders for homeowners explains how those work.
What kitchen design decisions for a new home get forgotten?
The forgotten ones are usually small and functional. They don’t show up in the design photos, so nobody thinks about them until move-in day. These are the kitchen design decisions for a new home I see missed most:
Trash and recycling pull-outs. Size and location.
Outlets on the island. Code often requires some, and you’ll want them where you actually use a mixer.
Under-cabinet lighting. Much easier to plan before drywall.
Panel-ready appliance panels. Who supplies them, the cabinet shop or the appliance vendor?
Toe kick and filler details. Especially next to the refrigerator and walls.
Window trim at the sink. How the backsplash meets the window.
Allowance tracking. Whether each item is inside its allowance. See how construction allowances work.
How do you keep every kitchen decision in one place?
Write every selection down with the item, the model or color, the finish, the supplier, the cost against the allowance, and the date you approved it. One sheet per room. Your builder should have a version of this, and it helps a lot if yours matches theirs.
The Custom Home Selection Sheet Template is the same set of sheets builders use, and it works just as well for homeowners who want every kitchen decision in one place.
When a question comes up on site, and one will, you open the sheet instead of digging through texts and emails. That alone saves a lot of back and forth.
Frequently asked questions
When should I start kitchen selections for a new home?
Start as soon as the plans are close to final, before construction begins if you can. Appliances and cabinet layout need to be settled before rough-in.
Should I pick countertops or cabinets first?
Choose the cabinet layout first, since the countertop is cut to fit it. For colors, many people pick the countertop first and match the cabinet finish to it, because slabs vary more and are harder to change.
What happens if my kitchen selection goes over the allowance?
You usually pay the difference, often with the builder’s markup, through a change order. Ask your builder how overages are billed before you start shopping.
How many kitchen decisions are there in a new home?
It varies with the home, but it’s easily dozens once you count every model, finish, and color. That’s why a written checklist and a schedule matter.
BTW, if you want every kitchen decision written down in one place before the cabinets get ordered, grab our Custom Home Selection Sheet Template over at the Building Optimal Shop. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.