Change Orders: What Homeowners Should Know Before Building

For homeowners, a change order is a written agreement with your builder to change something in the contract after it’s signed: the design, a material, a finish, or the scope. It states what’s changing, what it costs, and how it affects the schedule, and you sign it before the work happens. Change orders for homeowners are normal on almost every build. Understanding the process before you start is what keeps them from becoming expensive or stressful.

I write a lot of change orders. Most of them are good changes the homeowner is happy about. The bad ones are almost always the ones that weren’t written down.

What are change orders for homeowners?

Change orders are the formal way to make changes during construction. Your contract describes a specific house, built to specific plans and specifications, for a specific price. Anything you want different from that becomes a change order.

Common examples:

  • Design changes. Moving a wall, adding a window, enlarging a closet.

  • Upgrades. Better cabinets, a different countertop, more lighting.

  • Additions. Outlets, built-ins, a covered patio, a generator connection.

  • Allowance overages, in some contracts, are handled through change orders too.

  • Site conditions. Unforeseen rock or soil issues, depending on how your contract handles them.

A good change order is short, clear, and signed before the work starts. Builders use them to protect both sides. You should want them too.

What is the change order process for owners?

The change order process for owners usually follows the same basic steps, though every contract has its own details:

  1. You ask for a change. Ideally in writing, to your builder, not to the trade on site.

  2. The builder prices it. They may need quotes from trades and suppliers, so this can take a few days.

  3. You get a written change order. It describes the change, the cost, any fee, and any schedule impact.

  4. You sign it, and often pay a deposit or the full amount, depending on the contract.

  5. The work happens.

  6. It shows up in your records. Your contract price gets updated and your lender may need a copy.

Read your contract’s change order section before you sign. Our guide to a change order clause in a construction contract explains what a good one includes.

What is the cost of changes in a new home?

The cost of changes in a new home depends on what’s changing and when. The same change can be cheap in design and expensive in the field.

What goes into the price:

  • Materials and labor for the new work

  • Credit for what’s removed, if anything, which is often less than you’d expect if materials were already bought

  • Rework. Tearing out or redoing work already completed

  • The builder’s fee or markup. Most contracts allow one, and it’s fair, since managing changes takes time

  • Schedule impact. Delays can carry their own cost, especially with a construction loan accruing interest

Say you want to add a window to the dining room. During design, it’s a line on a drawing. After framing, it’s a structural change and a new window order. After drywall, it also means patching and repainting. Same window, three very different prices.

If you want to see how builders calculate the fee, our article on change order markup lays it out.

How do changes during construction affect the schedule?

Changes during construction almost always add time. The work itself takes time, and so does pricing it, ordering materials, and rescheduling trades.

  • Lead times. A new window or a different tile might take weeks to arrive.

  • Trade rescheduling. If one trade waits, the trades behind it wait too.

  • Inspections. Some changes need a revised permit or re-inspection.

A good change order states the schedule impact. If yours doesn’t, ask.

How do you avoid expensive change orders?

Make decisions early. The biggest lever you have is finishing design and selections before construction starts.

  • Finish the plans before you sign the contract

  • Make selections early, starting with long-lead items

  • Use the pre-drywall walk to catch outlet and blocking changes while they’re cheap. See the pre-drywall walkthrough checklist

  • Keep a list of ideas and bring them all to your builder at once, instead of one at a time

  • Never ask the trades directly. It skips pricing and documentation, and causes disputes

  • Ask for the price before saying yes

Our Home Construction Checklist (Homeowner Edition) puts decision deadlines in each phase, which is the best way I know to keep changes few and early.

What should every change order include?

Before you sign, check that it has:

  • A clear description of the change

  • The cost, including any fee or markup

  • Any credit for removed work

  • The schedule impact

  • When and how you pay

  • Signatures and dates from both of you

Keep every signed change order. They’re part of your contract, and your lender, your builder, and your future self will all need them. Our construction change order example shows what a complete one looks like.

Frequently asked questions

Why do builders charge a fee on change orders?

Managing a change takes time for pricing, ordering, scheduling, and supervision. Most contracts allow a fee or markup to cover that, and it should be stated in the contract.

Can I make a change without a change order?

You shouldn’t. Verbal changes lead to disputes over cost and scope. Put every change in writing and sign it before the work starts.

Do change orders affect my construction loan?

They can. Your lender may need to approve changes that affect the budget, and the extra cost often comes from your own funds. Ask your lender how they handle it.

When is the cheapest time to make a change?

During design, before the contract is signed. After that, earlier is cheaper than later.

BTW, if you want your decision deadlines laid out so changes stay early and few, grab our Home Construction Checklist (Homeowner Edition) over at the Building Optimal Shop. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.

Previous
Previous

How to Read Construction Plans: A Homeowner's Guide

Next
Next

How to Budget for Building a House (Without Surprises)