Appliance Selections for New Construction: Decide Before Cabinets

Appliance selections for new construction should be finished before cabinets are designed, because the exact model of each appliance sets the cabinet openings, the gas and electrical rough-in, the hood venting, and the water lines. Pick your full kitchen appliance package with model numbers during design or early pre-construction, get the spec sheets to your builder, and confirm delivery timing well before the cabinets are installed.

I see this one go sideways more than almost anything else in the kitchen. A homeowner picks cabinets, then falls for a range that’s six inches wider. Now somebody is rebuilding a cabinet. Appliances first saves everyone that conversation.

Why should appliance selections come before cabinets?

Because cabinets are built around appliances, not the other way around. The cabinet designer needs the exact width, height, depth, and installation requirements for every appliance to draw the layout. A built-in refrigerator, a 36-inch versus 48-inch range, or a drawer microwave each changes the cabinet design.

Appliances also drive rough-in:

  • Range or cooktop. Gas line, electrical circuit size, or both for dual fuel.

  • Wall ovens. Dedicated circuits and specific cabinet cutout sizes.

  • Hood. Duct size, duct route to the outside, and possibly make-up air, depending on the hood size and your local code.

  • Refrigerator. Water line location and, for built-ins, an exact opening.

  • Dishwasher. Water, drain, and power next to the sink.

If these aren’t settled before framing and rough-in, someone guesses. Guesses get expensive.

What goes into an appliance package for a new home?

An appliance package for a new home usually includes the core kitchen appliances, and sometimes laundry and extras. Here’s a full checklist:

  1. Cooking. Range, or cooktop plus wall ovens, and any speed oven or steam oven.

  2. Ventilation. Wall hood, island hood, hood insert, or downdraft.

  3. Refrigeration. Refrigerator, separate freezer column, beverage center, wine fridge, or ice maker.

  4. Cleaning. Dishwasher, second dishwasher, and disposal.

  5. Microwave. Drawer, built-in, over the range, or countertop.

  6. Laundry. Washer and dryer, if included, plus gas or electric dryer and venting.

  7. Outdoor kitchen. Grill, outdoor fridge, and burners, if you’re building one.

For each one, get the model number and the installation guide, not only the product page. The installation guide has the cutout dimensions and utility requirements.

How does an appliance allowance work?

An appliance allowance is a dollar amount in your contract for appliances you’ll select later. If your package costs more, you usually pay the difference through a change order. If it costs less, you may get a credit, depending on the contract.

Ask these before you shop:

  • What’s included? Delivery, installation, haul-away of packaging, and connection kits may or may not be in the allowance.

  • Who buys them? Some builders purchase appliances. Others let the homeowner buy directly.

  • Who stores them? Appliances often arrive before the house is ready. Someone needs a secure place to keep them.

  • How are overages billed? Ask whether the builder’s markup applies.

The article on construction allowances covers how these work in the contract.

How do you plan kitchen appliances around how you cook?

Start with your habits, not the brochure. Good kitchen appliance planning comes down to a few honest questions:

  • How often do you cook, and for how many? A huge range is great for big family dinners and wasted on takeout.

  • Gas or induction? This affects rough-in, so decide early.

  • Do you bake a lot? Two ovens may matter more than six burners.

  • How much cold storage do you use? Big families and bulk shoppers may want a separate freezer.

  • Do you want panel-ready appliances? Panels match the cabinets but add cost and coordination between the cabinet shop and the appliance supplier.

  • Where does the microwave go? It’s the appliance most people forget to place.

When are appliance selections for new construction due?

Appliance selections for new construction are typically due during design or pre-construction, before the cabinet layout is finalized and before rough-in. Ordering can come later, but the decision with model numbers needs to be locked early. Your builder’s selections schedule should show the date.

A practical sequence:

  1. Choose the package and model numbers during design.

  2. Send spec sheets to the builder, architect, and cabinet designer.

  3. Confirm rough-in requirements with the builder before framing is complete.

  4. Place the order with enough lead time, especially for specialty items.

  5. Schedule delivery for after cabinets and countertops, unless installation requires otherwise.

How do you avoid appliance mix-ups?

Write it all down: appliance, brand, model number, finish, dimensions, fuel type, panel-ready or not, supplier, price against the allowance, and delivery date. Then make sure the cabinet drawings show the same model numbers. That one comparison catches most problems.

The Custom Home Selection Sheet Template is the same set of sheets builders use, and it keeps every appliance and model number in one place.

If a model is discontinued mid-build, and it happens, tell your builder right away and send the replacement spec sheet before anyone orders. For the rest of the kitchen, see the kitchen selections checklist and cabinet selections for new construction.

Frequently asked questions

Can I change appliances after the cabinets are ordered?

Sometimes, if the new model has the same dimensions and utility needs. A different size or fuel type often means a cabinet change and a change order.

Should I buy appliances myself or through my builder?

It depends on your contract. Buying through the builder can simplify coordination and warranty questions, while buying yourself may give you more control over price and timing.

When should appliances be delivered?

Usually near the end, after cabinets and countertops are installed and the house can be secured. Confirm the date with your builder.

What is make-up air for a range hood?

It’s a way to bring outside air back in when a strong hood exhausts air from the house. Whether you need it depends on the hood and your local code, so ask your builder.

BTW, if you want every appliance model number written down before the cabinet shop starts drawing, grab our Custom Home Selection Sheet Template over at the Building Optimal Shop. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.