Electrical Walkthrough for New Construction: Outlets, Switches, More

An electrical walkthrough in new construction is a meeting at the house, after framing and before or during electrical rough-in, where you and your builder or electrician walk every room and confirm where each outlet, switch, light, fan, and data jack goes. You mark locations on the studs, adjust anything that doesn’t fit how you’ll live, and get the changes in writing. It’s one of the cheapest chances you’ll get to fix the house before drywall locks it in.

Skip the electrical walkthrough in new construction, and you find out on move-in day that the switch is behind the door swing, the bed wall has no outlet, and the TV spot has no power. Every one of those is a drywall patch, a paint touch-up, and a service call. Or you just live with it.

What happens during an electrical walkthrough in new construction?

You walk the framed house room by room with the electrical plan in hand. The electrician has usually marked box locations already, so you’re confirming, not designing from scratch.

Plan on an hour or two for an average house. Bring the plans, your furniture layout, a tape measure, a marker, and your phone for photos. If your builder does a separate pre-drywall walkthrough, the electrical walkthrough usually comes first, since it happens around rough-in.

What should you check on an electrical walkthrough, step by step?

Go room by room in the same order every time. Here’s the routine I’d follow:

  1. Stand at each door. Check the switch is on the latch side, not behind the door swing.

  2. Place your furniture. Mentally put the bed, sofa, desk, and TV where they’ll go.

  3. Check outlets against furniture. Nightstands, sofa ends, desk, TV wall.

  4. Look up. Confirm ceiling boxes for lights and fans are centered where you want them.

  5. Check three-way switches. Stairs, long halls, and rooms with two entrances.

  6. Check exterior. Porch lights, exterior outlets, holiday lighting outlets, landscape lighting.

  7. Check low voltage. Network, TV, doorbell, cameras, and speaker locations.

  8. Write down every change. Then get it confirmed in writing, with any cost.

Record every change on your selections list for that room. The Custom Home Selection Sheet Template is the same set of sheets builders use, handy for keeping every decision in one place, including electrical changes.

Where should outlets go? Outlet placement in new construction

Good outlet placement in new construction follows how you’ll actually use each room. Code sets minimums, and your electrician handles those. Your job is the extras. A checklist:

  • Both sides of the bed. Plus one near a nightstand for charging.

  • TV walls. An outlet and a data jack at mounting height, plus a conduit if you can.

  • Kitchen island. Where you’ll use a mixer, not only where code requires.

  • Inside cabinets or appliance garages. For a coffee maker or charging drawer.

  • Bathroom vanities. Inside a drawer or medicine cabinet for hair tools, if you want.

  • Garage. Workbench, freezer, ceiling outlet for a door opener, and a future EV charger circuit.

  • Exterior. Under eaves for holiday lights, at the patio, near the grill.

  • Floor outlets. In large living rooms where the sofa floats.

Code requirements vary by jurisdiction, so let your electrician and local building department handle that side.

Where should switches go? Switch placement in new construction

Switch placement in new construction should follow your path through the house. A few rules of thumb:

  • Latch side of every door. You shouldn’t reach behind a door to find a switch.

  • Both ends of stairs and long halls. Three-way switches.

  • Grouped and labeled. Kitchens and great rooms get crowded. Decide which switch does what.

  • Consistent height. Ask your builder their standard and stick to it.

  • Closet lights. Switch outside or a door-activated switch.

  • Exterior and garage lights. A switch at the door you’ll actually use.

What does a sample walkthrough change list look like?

Here’s a hypothetical change list from one bedroom, with round numbers:

  • Move switch to latch side of door. No charge, before wiring is pulled.

  • Add outlet on bed wall, right side. About $100.

  • Add TV outlet and data jack at 54 inches on opposite wall. About $200.

  • Center fan box on bed, not on room. No charge.

  • Total: About $300, approved by homeowner, dated.

That same list after drywall would cost more, because now someone has to cut, patch, and repaint. Pricing varies by builder and market, so get each change priced in writing.

Which electrical selections for a new home should be decided first?

Electrical selections for a new home that affect rough-in should be decided before the walkthrough. That means your light fixture types, fan locations, under-cabinet lighting, and any smart switches or special controls. The fixtures themselves can come later, but the box locations and wiring can’t. See lighting selections for new construction and low voltage prewire for new construction.

What are the most common electrical walkthrough mistakes?

Most mistakes come from rushing the walkthrough or not showing up with a furniture plan.

  • Not placing furniture. Outlets end up behind the sofa.

  • Forgetting the outside. Holiday and landscape lighting.

  • Skipping the garage. Future EV charger, freezer, workshop.

  • Verbal changes only. If it isn’t written down, it may not happen.

  • No photos. Take pictures of every wall before drywall for future reference.

The Custom Home Selection Sheet Template is the system that keeps those changes organized with every other selection, so nothing gets lost between the walkthrough and the final inspection. For the inspections around this stage, see new construction inspections.

Frequently asked questions

When should the electrical walkthrough happen?

After framing, when boxes are marked or set, and before wire is pulled or insulation goes in. Ask your builder to schedule it.

Do electrical changes cost extra?

Usually yes, though moving a box before wiring may be free. Ask your builder how changes are priced and get them in writing.

Can I add outlets after drywall?

Yes, but it costs more and means cutting and patching walls. It’s much easier during rough-in.

Should my designer attend the electrical walkthrough?

If you’re working with one, it helps. They can confirm fixture locations match the lighting plan.

BTW, if you want every outlet, switch, and lighting change from your walkthrough written down in one place, grab our Custom Home Selection Sheet Template over at the Building Optimal Shop. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.