A pre drywall walkthrough is a walk through the framed house after the plumbing, electrical, and HVAC are roughed in, but before insulation and drywall cover everything up. You check that outlets, switches, lights, plumbing, blocking, and framing are where you expect them, and you photograph every wall. It’s the last cheap chance to move things, and the best record you’ll ever have of what’s inside your walls.
I tell every client this is the most important walk of the job. Moving an outlet now is a small task. Moving it after drywall and paint is a patch, a repaint, and an awkward conversation.
What is a pre drywall walkthrough?
A pre drywall walkthrough is a scheduled meeting at the house with your builder, usually your superintendent or project manager, at the end of rough-in. Some homeowners also hire a third-party inspector for a pre drywall inspection at the same stage.
The walk has three goals:
Confirm locations. Electrical, plumbing, low-voltage, and blocking match what you selected and what you expect.
Catch mistakes. Missed items, wrong heights, things that changed since the plans were drawn.
Document the walls. Photos and video of every wall before it closes.
The city’s rough-in inspection usually happens around this time too, but that checks code, not your preferences. For how the inspections fit together, see our guide to new construction inspections.
How should you prepare for the walkthrough?
Bring the right documents and a plan. A little prep turns a pleasant tour into a useful meeting.
Bring the plans, including the electrical plan if you have one.
Bring your selection sheets. Fixture locations and sizes depend on what you picked.
Know your furniture. Where the bed, sofa, TV, and desk go decides where outlets and switches should be.
Charge your phone. You’ll take a lot of photos.
Bring painter’s tape and a marker if your builder is fine with you marking items.
Block out enough time. Rushing this walk defeats the purpose.
Pre drywall checklist: electrical and low voltage
Electrical is where most changes happen at this walk. Go room by room:
Outlets. Location, height, and count. Think about beds, nightstands, desks, and kitchen counters.
Switches. On the latch side of doors, at the right height, and controlling the fixtures you expect.
Light fixtures. Centered where they should be, like over the island, dining table, and vanity.
Exterior. Outlets, lights, and any power for landscape lighting or holiday lights.
Special circuits. Appliances, EV charging if planned, and any equipment you discussed.
Low voltage. Network drops, TV locations, speakers, cameras, doorbell, and alarm.
TV locations. Power and data at the right height for the TV you’ll actually hang.
Pre drywall checklist: plumbing, HVAC, and framing
These are harder to change, so you want to catch problems now.
Plumbing fixture locations. Sinks, toilets, showers, and tubs in the right spots. Shower valve and head heights match what you want.
Shower niches and benches. Framed where you expect, at the size you want.
Exterior hose bibs and gas stubs where you need them.
HVAC registers and returns. Not where furniture will block them.
Thermostat locations.
Blocking. For towel bars, grab bars, TV mounts, heavy mirrors, shelves, and cabinet hardware. This is one of the most valuable things to check.
Framing. Door and window openings match the plans, and walls look straight.
Attic access and ceiling details like trays and beams.
Your builder may not change everything on the spot. Some items need a change order. That’s normal, and our article on change orders for homeowners explains how that works.
How do you document a framing walkthrough?
Photograph every wall from a few angles, and take a slow video of each room. These photos are worth more than anything else you’ll collect during the build.
Use a reference point. Start each room from the door so you can tell later which wall is which.
Get close-ups of plumbing lines, wiring runs, and blocking.
Measure from fixed points for anything you might want to find later, like a stud or a pipe behind a shower wall.
Save them in one folder labeled by room.
Years from now, when you hang a heavy mirror or add a shelf, you’ll know exactly what’s behind the drywall.
What happens after the pre drywall walkthrough?
Your builder should send a written list of what was agreed: what will be moved, what needs a change order, and when it will be fixed. Read it carefully, and confirm before insulation starts.
A good sequence:
Get the written list within a day or two
Approve any change orders quickly so the schedule doesn’t slip
Confirm the corrections are made before insulation
Pass the city inspection
Insulation, then drywall
If you want this walk and the others in the order they come, our Home Construction Checklist (Homeowner Edition) lays out every step. For the walk at the end of the job, use our new construction walkthrough checklist.
Frequently asked questions
When does the pre drywall walkthrough happen?
After framing and all rough-ins are complete, and before insulation is installed. Ask your builder to schedule it as soon as the date is known.
Should I hire an inspector for the pre drywall inspection?
Many homeowners do, and it can catch workmanship issues that you might not recognize. Coordinate timing with your builder so it doesn’t delay the schedule.
Can I move outlets during the pre drywall walk?
Usually, yes, though it may require a change order depending on your contract. This is the cheapest time to move them.
What is the most commonly missed item at pre drywall?
Blocking for towel bars, grab bars, TVs, and heavy mirrors is often missed. Check it in every bathroom and wherever you plan to mount something heavy.
BTW, if you want this walkthrough and every other step of your build in the right order, grab our Home Construction Checklist (Homeowner Edition) over at the Building Optimal Shop. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.