A change order approval process is the set of steps a change goes through from request to signature before any work happens: the change is written up, priced, reviewed by the builder, presented to the client, signed by both parties, and logged. On a custom home, the client and the builder both sign, and sometimes the lender or architect does too. The rule that makes it work is simple: no signature, no work.
When there’s no defined process, approvals happen by text, by nod, or by a “sure, go ahead” in the driveway. Then the invoice shows up and the client remembers it differently. That’s how a $3,000 change turns into a $3,000 write-off and a client who doesn’t trust your numbers anymore.
Who approves a change order on a custom home?
At minimum, the client and the builder. The client approves the scope, price, and schedule impact. The builder approves that the price is right and the work is buildable. On some projects, other people need to sign or at least be notified.
The client. Every owner on the contract, or whoever the contract names as authorized to approve.
The builder. Usually the owner or project manager, per your internal authority limits.
The lender. Some construction loans require lender approval of changes above a certain size. See change orders and construction loans.
The architect or engineer. When a change touches design or structure.
Name the authorized signers in the contract. If only one spouse can approve, say so. If both must sign, say that.
The change order approval process, step by step
Capture the request in writing. Same day, with who asked and what they asked for.
Pause the work. Nothing changes on site until approval. This is the step that gets skipped.
Scope and price it. Get trade pricing, add your markup, and figure the schedule impact.
Internal review. Someone other than the person who priced it checks the math and the scope.
Present it to the client. In writing, with a decision deadline.
Get the signatures. Client and builder, plus any lender or design approval required.
Collect payment if your terms require it. Many builders collect before the work starts.
Release the work. Tell the trades, update the plans, and update the schedule.
Log it. Change order number, amount, days, and new contract total in your change order log.
If you want the forms and the system already built, our Custom Home Change Order Template is a template plus a guide for running a simple, profitable change order process.
What goes on a change order approval form?
A change order approval form needs enough detail that a stranger could read it a year later and know exactly what was agreed. Here’s the checklist:
Change order number and date. Sequential, no gaps.
Project and contract reference.
Description of the change. What’s added, removed, or substituted.
Reason. Client request, unforeseen condition, design change, code.
Price. Cost, markup, and total, or the credit.
Schedule impact. Days added, or “0 days.” Never blank.
Revised contract total.
Payment terms.
Signature and date lines. For every required approver.
Approval deadline. After which pricing may change.
Change order authorization: what counts as a valid sign off?
Change order authorization should be whatever your contract says it is, and your contract should say “written and signed.” A change order sign off can be a wet signature, a signed PDF, or an e-signature, as long as your contract allows it and it identifies the signer. Whether a particular signature method holds up varies by state, so ask your attorney what your contract should require.
What doesn’t count, in my book, is a text saying “ok,” a thumbs-up emoji, or a conversation. Those may or may not be enforceable, but they’re always arguable. See verbal change orders for why that matters.
Example: a change order moving through approval
A hypothetical change, start to finish:
Monday: Client asks to add two outlets on the island. PM writes it up.
Tuesday: Electrician prices it. PM adds markup. Total: $450, 0 days.
Tuesday afternoon: Office manager checks the math. CO #7 sent to client with Friday deadline.
Wednesday: Both clients e-sign. Builder signs.
Thursday: Payment received per terms. Electrician scheduled. Log updated: contract total revised.
Four days, no drama, and nobody has to remember anything later. The paperwork is what lets you skip the argument.
How long should change order approval take?
As short as possible without skipping steps. Small, simple changes can turn around in a day or two. Larger ones that need engineering or lender sign-off take longer. Put a response deadline on every change order so a pending decision doesn’t stall the job, and say in the contract what happens if the client doesn’t respond.
Approval process mistakes that cost builders
Starting work before the signature. You lose all leverage on price.
Letting the superintendent approve pricing in the field. Set authority limits.
Only one spouse signs. When the contract requires both.
No deadline. Decisions drift, and so does the schedule.
Billing at the end. Collected late, disputed often. See change order policies.
A change order approval process only protects you if you follow it every time. A consistent Custom Home Change Order Template keeps every request, price, and signature in the same format, so approvals are routine instead of negotiations.
Frequently asked questions
Can a superintendent approve a change order?
Only if your company gives them that authority, and usually only up to a set dollar limit. The client still has to sign.
Do both homeowners need to sign a change order?
It depends on your contract. Many builders require every owner on the contract to sign, which avoids disputes later.
Is an email approval of a change order enough?
It’s better than nothing, but a signed change order form is clearer. Your contract and state law determine what’s valid, so confirm with your attorney.
What if the client won’t approve a change order?
Then the work doesn’t proceed. Talk through the price, offer options, and document the decision either way.
BTW, if you want every change order to move through the same approval steps without reinventing the form, grab our Custom Home Change Order Template over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.