Change Order Email: How to Send One Clients Actually Approve

A change order email is the short message that delivers a priced change order to your client and asks for a decision by a specific date. It should say what changed, what it costs, how it affects the schedule, what you need from them, and by when, with the signed-ready change order attached or linked. Keep it under 150 words. The email gets the decision; the change order form is the record.

Most change order emails fail in one of two ways. They’re a wall of text the client doesn’t read, or they’re so casual (“hey, that outlet thing is $450, cool?”) that the reply becomes the contract. Either way, the decision sits in an inbox, the trades wait, and you end up arguing about what “cool” meant.

What should a change order email include?

Five things, in this order. If the client reads only the first two lines, they should still know what you’re asking.

  • Subject line with the CO number and the ask. “CO #7: Island outlets, approval needed by Friday.”

  • One-line summary. What’s changing and the total.

  • Schedule impact. Days added, or none.

  • The action. Sign the attached change order, and how.

  • The deadline. And what happens if it passes.

Leave the detailed pricing and scope in the attached form. The email is the cover letter, not the document. For what belongs on the form itself, see how to write a construction change order.

Change order email template

Here’s one you can adapt. Hypothetical numbers.

Subject: CO #7: Add two island outlets, approval needed by Friday 5/16

Hi Sam and Alex,

Attached is Change Order #7 for the two additional island outlets you asked about on Monday.

  • Total: $450

  • Schedule impact: 0 days

  • New contract total: shown on the form

Please review and sign by Friday 5/16 so the electrician can include it in this week’s rough-in. After that date, adding the outlets may cost more because the walls will be closed.

Happy to walk through it on a quick call.

Thanks,

[Name]

That’s the whole thing. Notice the deadline has a reason attached. Clients respond to reasons faster than to dates.

How to send one, step by step

  1. Finish the change order first. Price, scope, schedule, and signature lines. Never email a price you haven’t confirmed.

  2. Write the subject line. CO number, short description, and deadline.

  3. Write the summary. One sentence on what changed and why.

  4. List price, days, and new total. Three short lines.

  5. State the ask and the deadline. Give the reason for the deadline.

  6. Attach or link the form. E-signature if your contract allows it.

  7. Copy everyone who must approve. Both owners if the contract requires both.

  8. Follow up before the deadline. One reminder, then a call.

  9. File the signed copy. And update the change order log.

If you want the form, the process, and a cleaner way to present changes already worked out, our Custom Home Change Order Template is a template plus a guide for a simple, profitable change order system.

Change order letter sample vs email: which should you use?

Use the email for speed and the form for the record. A change order letter sample you find online is usually just a formal version of the same message, which made sense when everything went by mail. Today most clients respond faster to email, and an e-signed form gives you a cleaner paper trail than a letter.

A formal letter still makes sense for big or disputed changes, or when your contract requires written notice delivered a certain way. Check what your contract says about notice. If it specifies a method, use that method.

What is a change order notification?

A change order notification is a heads-up that a change is coming, sent before you’ve priced it. It’s useful when you discover a condition in the field, like rotten framing or rock in the excavation, and the client needs to know now that cost and time are likely to change.

Checklist for a good notification:

  • What you found. With photos.

  • Why it matters. What it affects.

  • What happens next. “We’re pricing it and will send a change order by Thursday.”

  • Any immediate decision needed. Like stopping work in that area.

  • Your contract’s notice requirement. Some contracts set deadlines for giving notice of a change.

What are the most common mistakes in these emails?

  • Approving by reply. “Sounds good” is not a signature. Ask for the signed form.

  • Burying the price. Put the total in the first three lines.

  • No deadline. Then no decision.

  • Emotional language. Keep it factual. Save explanations for the call.

  • Sending from a personal phone. Keep project communication in one system. See construction client communication plans.

  • Batching changes at the end. Send each one when it happens.

A good change order email takes five minutes when the change order behind it is solid. A consistent Custom Home Change Order Template gives you the same clean form every time, so the email only has to point at it. For handling the reply when a client balks, see change order negotiation.

Frequently asked questions

Can a client approve a change order by email?

Some contracts allow it, but a signed change order form is cleaner. Whether an email reply is enforceable varies by state and contract, so ask your attorney.

How fast should I send a change order to a client?

As soon as the change is priced. Same day as the request is ideal for small changes.

Should I explain my markup when I send a change order?

No. Your markup policy should already be in the contract. The email shows the total.

What if the client doesn’t reply by the deadline?

Call them. If there’s still no decision, document that the change is not approved and keep building to the original plans.

BTW, if you want every change order email to point to a form that’s already clear and complete, grab our Custom Home Change Order Template over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.