Change Order Delays: How to Price Time Into a Change Order

Change order delays are the extra days a change adds to the schedule, and they should be priced and written into the change order just like labor and materials. To do it, figure how many working days the change adds to the critical path, multiply those days by your daily cost of keeping the job open, and add that to the price along with a stated time extension. If a change adds no time, write “0 days.” Never leave it blank.

Builders price the work and forget the time. Then the job finishes three weeks late, the client is angry about the delay, and the contract says the completion date never moved. You paid for those three weeks in supervision, interest, and rentals, and you might be on the hook for delay damages too.

Why do change order delays matter so much?

Because time costs money on both sides. For you, every extra week means superintendent time, insurance, equipment, temporary utilities, and overhead. For the client, it can mean more construction loan interest, more rent, and a later move-in. If the change order doesn’t say the date moved, the contract still holds you to the old one.

The schedule impact of change orders is also cumulative. Five changes that each “only add a day” are a week. Track the total. For the bigger picture on delays, see construction delays on a new home.

How do you calculate change order days added?

Look at whether the change touches the critical path, the sequence of tasks that sets the finish date. If it does, the days it adds to that path are the days added. If it happens in parallel with other work and doesn’t push anything, it may add zero.

  • Direct work time. How long the added work takes.

  • Waiting time. Lead time on materials, engineering, or permits.

  • Re-sequencing. Trades that have to come back or wait.

  • Inspection time. Re-inspections added by the change.

  • Float used. If the change eats slack in the schedule, note it even if the finish date holds.

Use your actual schedule, not a guess. See custom home construction schedules for how to build one you can use this way.

How to price time into a change order, step by step

  1. Know your daily general conditions cost. Supervision, insurance, rentals, temporary facilities, and overhead per working day. See general conditions.

  2. Price the work itself. Trades and materials, with markup.

  3. Determine days added to the finish date. Using your schedule.

  4. Multiply days by daily cost. That’s the time component.

  5. Add it as its own line. So the client sees it.

  6. State the time extension. “Contract completion date extended by X working days.”

  7. Update the schedule and tell the trades. After the change order is signed.

If you want a form that already has a place for time and price on every change, our Custom Home Change Order Template is a template plus a guide for a simple, profitable change order system.

Example: a change order with days added

Hypothetical, round numbers. The client adds a covered porch extension after framing.

  • Framing, roofing, concrete, electrical, with markup: $14,000

  • Engineering revision: $800

  • Days added to the critical path: 6 working days

  • Daily general conditions cost (your number): $400 per working day, for illustration

  • Time component: 6 × $400 = $2,400

  • Change order total: $17,200

  • Change order time extension: completion date extended by 6 working days

Without the time line, you’d have absorbed $2,400 and still owed the old completion date. With it, the client sees what the change really costs and agrees to the new date in writing.

What is a change order time extension?

A change order time extension is the written agreement that the contract completion date moves because of the change. It protects you from delay claims for time the client’s change caused. Some contracts allow a time extension without added cost, such as for weather. Others tie both together.

Checklist for a clean time extension:

  • Number of days. Working or calendar, as your contract defines.

  • New completion date. Spelled out.

  • Reason. Tied to the change.

  • Cumulative days to date. Total extensions on the job.

  • Signatures. Same as the price.

How delay damages and extensions work depends on your contract and your state, so have your attorney review that language.

How to talk to clients about schedule impact

Tell them before you price it. “This will likely add about a week” is a sentence clients can handle on day one. It’s a lot harder on the day they expected to move in.

  • Give time and cost together. Never one without the other.

  • Show the ripple. Which trades move and why.

  • Offer a no-time option. Sometimes a change can wait until after closing.

  • Report the running total. Days added to date, on every update.

Common mistakes with change order delays

  • Leaving the days blank. A blank reads as zero, and it’s hard to argue otherwise later.

  • Not charging for time. Overhead keeps running.

  • Calendar vs working days confusion. Define it in the contract.

  • Not updating the schedule. The trades work off the old plan.

  • Adding days later. Time claims made at the end look like excuses.

Change order delays are predictable if you price them every time. A consistent Custom Home Change Order Template puts price and days side by side on every change, so the schedule and the contract never drift apart. Keep the running total in your change order log.

Frequently asked questions

Can I charge for delays caused by a client change?

Usually, if your contract allows it and the change order states it. Put the time cost on the change order so it’s agreed before work starts.

Should I use working days or calendar days?

Either works if the contract defines it. Many residential builders use working days to account for weekends and holidays.

What if a change order adds no time?

Write “0 days” on the form. It shows you considered the schedule and the completion date stands.

Do weather delays need a change order?

It depends on your contract. Many contracts treat weather as an excusable delay that extends time without added cost, documented in writing.

BTW, if you want every change order to account for the days as well as the dollars, grab our Custom Home Change Order Template over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.