A subcontractor scope of work is a written description of exactly what a trade will furnish and install, what’s excluded, which plans and specs govern, and what “complete” means for that trade. A good one names the materials, the quantities or references, the cleanup, the inspections, and who handles the gray areas between trades. If two reasonable people could read it and disagree, it isn’t done yet.
Most fights with trades aren’t about money or quality. They’re about what was included. The framer thought the blocking was the drywall guy’s problem. The plumber thought the gas line was the HVAC sub’s problem. A written scope settles those arguments before anybody has to have them.
What should a subcontractor scope of work include?
Every subcontractor scope of work should cover the same core sections, no matter the trade:
Project and documents. Address, plan set and revision date, specification document, and any engineering. “Per plans dated” is one of the most useful phrases in construction.
Inclusions. What the trade furnishes and installs, in plain language. Labor, materials, equipment, and any permits they pull themselves.
Exclusions. What is specifically not included. This is the section that prevents the most arguments.
Builder-furnished items. Anything you supply that they install, like fixtures, appliances, or windows.
Interfaces with other trades. Who does the blocking, the sleeves, the penetrations, the patching.
Inspections and corrections. Who schedules inspections, who attends, and who pays for re-inspections caused by their work.
Cleanup and site rules. Daily cleanup, debris removal, and where their trash goes.
Completion standard. What has to be true before they invoice the final payment, including punch items.
How do you write a trade scope of work that prevents fights?
Write the trade scope of work around the handoffs, because that’s where the fights live. The middle of a trade’s work is rarely the problem. The edges are.
Be specific about the gray areas. Fire blocking, backing for cabinets and grab bars, attic access framing, dryer vent routing, hose bibs, and exterior penetrations all need an owner.
Reference the spec, not your memory. If the spec says a certain grade of drywall in wet areas, the scope should point to it. My piece on how to write construction specifications covers the other half of this.
Use the word “including.” “Install all exterior trim, including frieze boards, corner boards, and window casing” beats “install exterior trim.”
State quantities when they matter. Number of outlets, linear feet of fence, number of hose bibs. If it changes, you have a basis for a change order.
Write exclusions as carefully as inclusions. “Excludes gas line to range” is one line that can save an afternoon of arguing.
Is there a good scope of work template for construction?
A good scope of work template for construction has a fixed structure with trade-specific sections underneath. Keep the general terms the same for everyone, then build a library of trade scopes you reuse and improve after each job.
Here’s how I’d set it up:
A general section that applies to every trade: site rules, cleanup, safety, insurance requirements, payment process, and how changes get approved.
A trade section for framing, plumbing, electrical, HVAC, insulation, drywall, trim, paint, and so on, each with inclusions and exclusions.
A project section that lists the plans, specs, and anything unusual about this particular house.
Every time a trade asks “is that included?” on a job, the answer goes into the template for next time. After a few houses, your scopes get very hard to argue with.
How is a scope of work for subcontractors different from the agreement?
The agreement sets the legal relationship. The scope of work for subcontractors sets the work. The subcontractor agreement covers things like insurance, indemnity, warranty, payment terms, and termination, and it usually stays the same from job to job. The scope changes with each project and each trade.
I like the scope attached to the agreement as an exhibit, or issued as a job-specific document that references the master agreement. Either way, have your attorney review how they tie together, because the legal structure varies by state.
What does a scope of work example look like?
Here’s a short example for a painting scope on a hypothetical 3,000 square foot house. Yours would be longer.
Inclusions. Prime and two finish coats on all interior walls and ceilings per the paint schedule. Caulk and fill all trim nail holes. Paint all interior doors and trim in the specified sheen. Two coats on exterior trim and siding per the spec.
Exclusions. Cabinet finishing. Staining of stair treads. Drywall repairs beyond normal touch-up.
Builder-furnished. None. Paint purchased by the trade per the spec.
Interfaces. Touch-up after the final trim and hardware install. One return trip for punch included.
Completion. Final payment released after the builder’s punch walk and correction of listed items.
Notice the return trip. If you don’t say how many trips are included, you’ll find out the hard way that the answer was zero.
When should you send the scope?
Send it with the bid request, not after you’ve picked the trade. If you send plans and ask for a number, each trade bids their own version of the job, and you end up comparing three different scopes. Send the scope first and you get comparable numbers. That’s the whole point of subcontractor bid comparison.
The scope is one piece of the trade paperwork I want in place before anybody starts. Our Subcontractor Paperwork Package handles the onboarding letter and insurance tracking that sit alongside it.
Frequently asked questions
Who writes the subcontractor scope of work?
The builder should. Trades will happily write their own, and it will be written in their favor. Use their proposal as an input, then issue your scope.
How detailed should a scope of work be?
Detailed enough that a new trade who has never worked for you could price it and do it. If you have to explain it on site, it belongs in the document.
What happens if work is not in the scope?
It becomes a change, priced and approved before it’s done. That’s exactly why the exclusions section matters.
Should the scope of work be signed?
Yes. It should be signed or clearly incorporated into the signed agreement. Ask your attorney how to tie the two documents together in your state.
BTW, if you want a scope of work backed by the rest of your trade paperwork, grab our Subcontractor Paperwork Package over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.