Subcontractor bid comparison, also called bid leveling, is the process of adjusting competing trade bids so they cover the same scope, then comparing the adjusted totals. You list every item each bid includes and excludes, add a cost for anything missing, and only then look at the price. The lowest number on the page is often not the lowest number once the bids are level.
I’ve seen plenty of builders hire the cheap bid and pay for it twice. Not because the trade was dishonest, but because the bid quietly left something out and nobody caught it until the house was framed. Bid leveling is a boring hour that saves an expensive month.
What is bid leveling?
Bid leveling is making bids comparable. Three plumbers will send you three different documents with three different assumptions. One includes fixtures. One excludes the gas line. One assumes a smaller water heater than your spec. Leveling means you put all three on one sheet and fill in the holes until each one prices the same house.
The goal isn’t to find the cheapest trade. It’s to find the best value for the same scope, and to know exactly what you’re buying.
How do you compare construction bids step by step?
Here’s the process I’d use for comparing construction bids:
Send everyone the same scope. Same plans, same specs, same written subcontractor scope of work, same due date. Most leveling problems start with a bid request that said “here are the plans, send me a number.”
Build a comparison sheet. One row per scope item, one column per bidder. Inclusions, exclusions, allowances, and assumptions all get a row.
Mark each line. Included, excluded, or unclear. Unclear counts as excluded until the trade confirms in writing.
Price the gaps. If bidder B excluded the gas line, add what it would cost you to get it done, from their own number or another trade’s.
Normalize allowances. If one bid carries a fixture allowance and another includes specified fixtures, adjust so they match your spec.
Check the math and the terms. Payment terms, deposit requirements, warranty, and the bid’s expiration date.
Compare adjusted totals. Now the numbers mean something.
Call to clarify before you award. Ask the leading bidder to confirm the gaps in writing.
How do you get apples to apples bids?
You get apples to apples bids by controlling the request, not by fixing the responses. The more you define up front, the less leveling you do later.
Specify products. Brand-neutral is fine, but name the grade, size, and type. “Water heater per spec section” beats “water heater.”
Give quantities. Count outlets, fixtures, openings, and linear feet when they drive the price.
Ask for a breakdown. Labor and materials separated, or at least major scope pieces separated.
Provide a bid form. If every trade fills out your form, comparing is easy. If every trade sends their own, you’re a translator.
Ask them to list exclusions. Make it a required section.
Your budget and specs drive all of this. If they’re thin, your bids will be all over the place. See construction budget and specifications.
What does a subcontractor bid comparison example look like?
Say you get three electrical bids on a 2,800 square foot house:
Bidder A: $30,000. Excludes light fixture installation and the low-voltage prewire.
Bidder B: $34,000. Includes fixture install. Excludes low-voltage.
Bidder C: $36,500. Includes everything in the scope.
Now level them. Suppose fixture install would run about $2,500 and the low-voltage prewire about $2,000 if bought separately. Bidder A becomes $34,500. Bidder B becomes $36,000. Bidder C stays at $36,500. The $6,500 spread on paper is actually a $2,000 spread, and you haven’t yet considered who shows up on time. These are made-up numbers, but the pattern is real: the gaps hide in the exclusions.
What should you look at besides price?
Price is one input. Before awarding, I’d also look at:
Schedule. When can they start, and how long will they take? A trade who can’t start for six weeks costs you carrying costs.
Insurance and paperwork. Can they produce a current certificate from their agent? See certificate of insurance in construction.
Track record. References from other builders, recent work you can see.
Payment terms. Large deposits or unusual draw requests are worth a conversation.
Communication. How fast and how clearly did they answer your questions during bidding?
Once you award, the trade still needs to be onboarded before the first day. Our Subcontractor Paperwork Package covers the onboarding letter and insurance tracking for that step.
How often should you rebid trades?
Rebid on a schedule, not in a panic. Many builders rebid each major trade every year or two, or when the plan type changes significantly. Constant rebidding burns relationships, because good trades get tired of pricing work they don’t win. Never rebidding means you lose touch with the market.
A middle path: keep your primary trade on a negotiated price that you check against one or two competitive bids on a regular cycle. If the gap gets wide, have the conversation.
Frequently asked questions
How many bids should I get per trade?
Three is typical for a new scope. Fewer if you have a trusted trade and are just checking the market. More than that and the comparison work outweighs the benefit.
Should I always choose the lowest bid?
No. Choose the best value after leveling. A slightly higher bid from a reliable trade often costs less once you count delays and callbacks.
Can I share one sub’s price with another?
I wouldn’t. It damages trust and good trades talk to each other. Ask them to sharpen their number without showing the competitor’s bid.
What is a bid leveling sheet?
A spreadsheet with scope items as rows and bidders as columns, used to mark inclusions, exclusions, and adjustments. It turns different proposals into comparable totals.
BTW, if you want the trade you just picked set up properly before the first day, grab our Subcontractor Paperwork Package over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.

