The phases of architectural design for a home are usually schematic design (SD), design development (DD), and construction documents (CDs), with a programming step before and bidding and construction support after. Schematic design sets the big picture, design development locks in materials and systems, and construction documents produce the detailed plans your builder prices and builds from. Each phase gets more detailed, and each one makes changes more expensive.
Why should a homeowner care? Because the cheapest time to change your house is in SD, and the most expensive time is after construction starts. People who don’t understand the phases tend to make big decisions late, and late decisions show up as redesign fees, permit delays, and change orders. Knowing where you are tells you what’s still cheap to change.
What are the phases of architectural design?
Most residential architects follow some version of this sequence. Names vary a little, but the work is the same.
Programming (pre-design). What you need, how you live, the budget, and what the lot and local rules allow.
Schematic design (SD). Rough floor plans, basic elevations, and how the house sits on the lot.
Design development (DD). Refined plans with materials, windows, structure, and systems chosen.
Construction documents (CDs). The full technical set for permit and construction.
Bidding or negotiation. The builder prices the plans and you sign a construction contract.
Construction administration (CA). The architect answers questions and visits the site, if that’s in their contract.
Your builder should be involved from SD on. That’s the single best way to keep the design tied to a real number. For the full step-by-step, see how to work with an architect.
What happens in schematic design?
Schematic design is where the house takes shape. The architect turns your wish list into a few layout options, then refines the one you like best.
At the end of SD you’ll typically have:
A floor plan with room sizes and how spaces connect.
Basic exterior elevations showing the style and roof shape.
A site plan showing where the house sits, the driveway, and setbacks.
A rough square footage the builder can use for a ballpark price.
This is the phase to move walls, change room sizes, and argue about whether you really need the bonus room. Changes here mostly cost the architect’s time.
What is the design development phase?
The design development phase turns a good layout into a specific house. Materials, window sizes, structure, mechanical systems, and key details get decided.
In DD you’ll usually work through:
Exterior materials. Brick, stone, siding, stucco, and roofing.
Windows and doors. Sizes, styles, and operation.
Structure. The engineer gets involved with beams, foundation, and framing.
Systems. HVAC approach, water heating, and major electrical needs.
Interior details. Ceiling heights, built-ins, and the kitchen layout.
This is when the builder can give a much tighter estimate. If DD comes in over budget, it’s far cheaper to adjust now than after the CDs are drawn. Builders have their own version of this list in the design development checklist.
Keeping all three parties aligned through DD is the hard part. The Checklist for Architects is the checklist builders use to align the client, architect, and builder during design, and it shows homeowners what needs settling at each phase.
What is the construction documents phase?
The construction documents phase produces the detailed drawings and specifications used for permits, pricing, and building. Think of it as the instruction manual for your house.
A typical CD set includes site plans, dimensioned floor plans, elevations, sections, roof plan, electrical layout, door and window schedules, structural drawings, and details for how things connect. Specifications describe the quality and products. Your builder should review the set for gaps before it goes to permit.
Changes during CDs aren’t impossible, but they ripple. Move one window and the elevations, sections, schedules, and structure may all need updating.
How long do the phases of architectural design take?
It varies with the size and complexity of the house, how quickly you make decisions, and how busy your architect is. As a general pattern, SD and DD are where homeowner decisions drive the timeline, and CDs depend more on the architect’s production time and engineering.
Permits come after CDs and can add their own time, which varies a lot by jurisdiction. Ask your architect for a schedule with target dates for each phase, and ask your builder how long local permits are taking right now.
Example: one decision through SD, DD, and CDs
Here’s how a single item, a kitchen island, moves through the phases:
SD: “Large island with seating for four, facing the family room.”
DD: Island size set, sink located in the island, stone top selected as a type, pendant locations sketched.
CDs: Exact dimensions, plumbing and electrical locations, outlet requirements, cabinet layout, and any support for an overhang.
Same island, three levels of detail. Changing it from four seats to six is easy in SD and a real redesign in CDs.
Mistakes homeowners make in the design phases
Most of them come down to deciding too late or approving too fast.
No budget check after SD. Get a builder’s number early.
Rubber-stamping DD. This is the phase to slow down and ask questions.
Big changes in CDs. They cost time and fees.
Skipping builder review. Gaps become change orders. See change orders for homeowners.
If you want one list to follow through every phase of design, the Checklist for Architects keeps the whole team working in the same order.
Frequently asked questions
What does SD DD CD mean in architecture?
They stand for schematic design, design development, and construction documents. They’re the three main phases most architects use to take a home from idea to buildable plans.
Do all architects use the same design phases?
Most follow a similar sequence, though some combine phases on smaller projects. Ask your architect to explain their process and what you approve at each step.
Are architect fees split by phase?
Often, yes. Many contracts bill a portion of the fee at the end of each phase. Read your contract for the exact structure.
When should the builder get involved in design?
Ideally during schematic design. That’s when cost feedback can still shape the house without expensive rework.
BTW, if you want a clear list of what to decide in each phase of design, grab our Checklist for Architects over at the Building Optimal Shop. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.

