Design Development Checklist: What to Resolve Before CDs

A design development checklist is the list of decisions a builder, architect, and client need to settle before construction documents start: structure, exterior materials, windows and doors, mechanical systems, plumbing and electrical intent, interior details, and an updated budget. If those items are resolved in DD, the CD set comes out clean and priceable. If they’re not, you get drawings full of “TBD” and a bid full of allowances.

Here’s why it matters to builders. Every unresolved item in DD becomes a question during CDs, an assumption during pricing, and a change order during construction. That’s lost margin, lost schedule, and a client who feels like the price keeps moving. A good DD review is the cheapest defense you’ll ever play.

What is the design development phase?

Design development is the middle phase of design, after schematic design and before construction documents. The layout is mostly settled, and now the team decides what the house is made of and how it works.

For builders, DD is the first point where you can give a real estimate instead of a ballpark. It’s also the last point where changes are relatively cheap. If you’re not reviewing the design here, you’re pricing someone else’s guesses later. For a homeowner-friendly overview, see phases of architectural design.

Design development checklist: what to resolve before CDs

Here’s the DD checklist architecture teams and builders should work through together:

  • Soil and site. Soil report in hand, foundation type chosen, grading and drainage concept set.

  • Structure. Engineer engaged, major beams and spans identified, framing approach agreed.

  • Exterior envelope. Wall cladding, roofing, trim, and the key details at transitions.

  • Windows and doors. Sizes, operation, product line or quality level, and egress checked.

  • Mechanical. HVAC system type, equipment locations, and duct or chase space.

  • Plumbing. Fixture locations, water heater type, gas needs, and any special items.

  • Electrical. Service size assumptions, lighting approach, low voltage, and any generator or solar.

  • Interior. Ceiling heights, stair design, built-ins, kitchen and bath layouts.

  • Finish level. A clear standard for flooring, tile, cabinets, and fixtures, even if exact selections come later.

  • Code and approvals. Zoning, setbacks, height, and any HOA or review board requirements.

  • Budget update. A builder estimate tied to the DD set, reconciled to the client’s number.

That’s a lot to keep straight across three parties. The Checklist for Architects is the list I’d hand an architect to align client, architect, and builder during design, so DD items don’t slide into CDs unanswered.

What are the design development deliverables?

Design development deliverables are the drawings and documents that show the decisions above. They’re more detailed than SD and less detailed than CDs.

A typical residential DD package includes:

  • Refined floor plans with dimensions, wall types, and door and window locations.

  • Exterior elevations with materials called out.

  • Building sections showing ceiling and plate heights.

  • Preliminary structural layout from the engineer.

  • Outline specifications describing materials and quality level. See outline specifications.

  • Preliminary lighting and electrical layout.

  • Kitchen and bath plans with key elevations.

How to run a design development phase checklist review

Run it as a meeting with a decision log, not an email chain. Here’s the process I’d use:

  1. Get the DD set and outline specs a few days before the meeting.

  2. Mark it up. Flag missing info, cost drivers, and anything that’s hard to build.

  3. Price it. Even a rough update by cost code beats a square-foot number.

  4. Meet with client and architect. Walk the list item by item.

  5. Record each decision. Who decided, what was decided, and the cost effect.

  6. List open items with an owner and a due date.

  7. Close open items before CDs start. Or agree in writing on an allowance.

Example: a DD checklist line item

Here’s a sample of how one line on a DD checklist should read:

  • Item: Great room rear wall glazing.

  • Status: Resolved.

  • Decision: Four large fixed units with two operable units, product line selected.

  • Structure: Engineer to size the header; steel not required.

  • Cost note: Within the window budget in the DD estimate.

  • Owner: Architect to show in CDs.

Compare that to a line that just says “windows TBD.” One prices cleanly. The other is a future argument.

Common mistakes in design development

The big one is treating DD like a formality on the way to permit drawings. Others:

  • No updated estimate. The budget drifts and nobody notices until bids come in.

  • Late engineering. Structure drives ceiling heights, beams, and foundation cost.

  • No space for mechanical. Ducts and equipment get squeezed in later.

  • Finish level undefined. “Nice” means different things to everyone.

  • Decisions in texts. If it’s not in the log, it didn’t happen.

When DD runs over budget, that’s the moment to design to the number. See design to budget for how builders and architects handle it.

Who owns the design development checklist?

The architect usually owns the drawings, but the builder should own the cost and buildability side of the checklist. The client owns the decisions. If nobody’s name is next to an item, it won’t get resolved.

I’d rather over-assign than under-assign. Every open item gets a name and a date. For more on how builders and architects split the work, see the builder-architect collaboration checklist. And if you want a ready-made list that covers each design stage, the Checklist for Architects keeps the team on the same page.

Frequently asked questions

What percentage of design is complete at DD?

There’s no fixed number, and it varies by firm. A good rule is that every major decision is made and only detailing and documentation remain for CDs.

Should the builder price the DD set?

Yes. A DD estimate is the best chance to catch budget problems before the expensive drawing phase starts.

What is the difference between DD and CDs?

DD decides what the house is and what it’s made of. CDs document exactly how to build it, in enough detail for permit and construction.

Can you skip design development on a small house?

Some teams combine phases on simple homes, but the decisions still have to be made. Skipping the review just moves them into construction.

BTW, if you want every DD decision resolved before CDs start, grab our Checklist for Architects over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.

Previous
Previous

Construction Drawing Checklist: What a Builder-Ready Set Includes

Next
Next

Phases of Architectural Design: SD, DD, and CDs Explained