How many change orders is normal on a custom home? There’s no official number, but it’s common to see somewhere between a handful and a couple dozen change orders on a custom build, depending on how complete the plans and selections were before construction started. What matters more than the count is the total: many builders consider changes adding a few percent to around 10 percent of the contract to be typical, and it varies a lot by home and market.
Change orders aren’t a sign that something went wrong. Too many change orders, especially late ones, usually are. They cost money, they add weeks, and they’re the most common reason homeowners and builders end up frustrated with each other halfway through a build.
How many change orders is normal? The average on a new home
There isn’t a reliable national average, and anyone who quotes you one is guessing. The average change orders on a new home depend on three things more than anything else:
How finished the plans were. A fully detailed set of drawings leaves fewer open questions.
How many selections were made before the start. Every finish decided later is a chance for a change.
The type of home. A production home with a fixed menu has very few. A one-of-a-kind custom home has more.
A homeowner who walks into construction with every selection made might see five or six small changes. A homeowner who is still designing the kitchen during framing might see thirty.
What change order percentage of contract is normal?
A common rule of thumb is that change orders on a custom home land in the low single digits to roughly 10 percent of the original contract. That’s a hedge, not a standard. Some homes end up near zero, and some double their budget because the owners kept adding scope.
Here’s a simple hypothetical example with round numbers:
Original contract: $700,000.
Change orders: 12 total.
Net added cost: $42,000 (upgrades, a few credits, one added window).
Change order percentage: $42,000 divided by $700,000 equals 6 percent.
Six percent on twelve changes would feel normal to most builders I talk to. Twelve changes adding $200,000 would not, even with the same count. Watch the dollars and the days, not the tally.
How many change orders is too many?
Too many change orders is less about a number and more about a pattern. These are the warning signs:
Changes after the work is done. Tearing out finished work costs far more than changing a drawing.
Changes that keep moving the finish date. Every few days added stacks up.
The budget gap keeps growing. You no longer know what the house will cost.
Your lender is asking questions. Construction loans have limits, and big changes may need approval or extra cash from you.
You’re making decisions on site, on the spot. That’s how regret happens.
If two or three of those are true, slow down and sit with your builder for a reset on scope and selections.
How to keep change orders under control
The honest answer to how many change orders is normal is “fewer than you think, if you plan.” Most change orders can be prevented before construction starts. Here’s the order I’d work in:
Finish the plans. Don’t break ground on drawings that still say “TBD.”
Make your big selections early. Cabinets, windows, plumbing fixtures, and appliances drive the rough-in.
Understand your allowances. Know what’s included and what happens if you go over. See how construction allowances work.
Keep a contingency. Hold money aside for changes and surprises. More in construction contingency.
Ask for the change order process in writing. How changes are priced, approved, and billed.
Batch small changes. Bring them to one weekly meeting instead of texting your builder ten times.
Sign before work starts. Always.
Builders who run a clean system make this easy on you. The Custom Home Change Order Template is the template and guide many builders use for a simple change order process, and it’s a good picture of what a well-run one looks like.
What does a change order cost beyond the price?
The price on the change order is only part of it. Most changes also carry costs that don’t show up as a line item:
Builder markup or fee. Usually applied to changes. Ask how.
Schedule days. Which may mean more construction loan interest and more months of rent.
Re-ordering and restocking. If a product was already ordered, there may be fees.
Re-inspection. Some changes trigger a new inspection or permit revision.
That’s why a “small” change near the end can cost more than a bigger one at the start. Our guide to change orders for homeowners walks through how they’re usually priced.
What should every change order include?
Every change order you sign should show what’s changing, the cost or credit, the schedule impact, and the new contract total. If it doesn’t, ask for it before you sign.
A number and date. So you can track them in order.
A clear description. What’s added, removed, or swapped.
The price. Including the builder’s markup or fee.
Days added. Or “0 days.”
Revised contract total. So the final bill isn’t a surprise.
Builders can see the full checklist in how to write a construction change order. Homeowners can use it to know what to expect.
How do you keep track of all your change orders?
Keep a simple running list: number, description, cost, days, and date signed. Add up the total every month and compare it to your budget and contingency. If your builder keeps a change order log, ask for a copy after each new change.
A builder who runs a written system, like the Custom Home Change Order Template, keeps every change numbered, priced, and signed, which means fewer surprises for you at the final draw.
Frequently asked questions
Are change orders bad on a new home?
No. Some changes are normal and even smart. The trouble starts when changes are late, undocumented, or keep growing the budget without a plan.
Can a builder refuse a change order?
Often, yes, depending on your contract. A builder may decline changes that affect structure, code compliance, or the schedule too much. Check your contract’s change clause.
Who pays for a change order caused by a code requirement?
It depends on the contract and why the requirement came up. Ask your builder and read the contract language, and talk to your attorney if the amount is significant.
Do change orders affect my construction loan?
They can. Lenders may need to approve changes, and you may have to cover added costs with your own cash. Ask your lender how they handle it before construction starts.
BTW, if you want to see what a clean, signed, numbered change order system looks like before your build starts, grab our Custom Home Change Order Template over at the Building Optimal Shop. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.