Change orders on a cost plus contract are still required, even though the client already pays actual cost plus your fee. A cost plus change order documents a change in scope, updates the estimated cost and your fee on that scope, notes any schedule impact, and gets the client’s signature before the work starts. The math is different from a fixed-price job, but the paperwork and the discipline are the same.
A lot of builders on cost plus skip change orders because “the client pays for everything anyway.” Then the final number lands 20 percent over the original estimate, the client can’t remember asking for half of it, and you spend the last month of the job defending invoices instead of finishing the house. On cost plus, the change order isn’t about getting paid. It’s about proving the client asked for it.
Do you need change orders on a cost plus contract?
Yes. A cost plus contract changes how the price is calculated, not whether scope changes need to be documented. If the client adds a covered patio, upgrades the windows, or moves a wall, you need a written record of what changed, what it’s expected to cost, and that they approved it.
Here’s why it matters more than people think:
The estimate is still a number the client remembers. Most cost plus jobs start with a budget. When the final cost runs past it, the client compares against that budget, not against actual cost.
Your fee rides on the change. If you charge a percentage fee, every added dollar of cost adds fee. Clients notice that. A signed change order shows the fee was agreed to up front.
Lenders want it. If there’s a construction loan, the bank needs to know the budget moved and who is covering the gap.
Schedule changes need a paper trail. Added scope usually adds days. Without a change order, a late finish looks like your problem.
If you’re still deciding between contract types, my take on cost plus vs fixed price covers the tradeoffs.
How does a cost plus change order work?
A cost plus change order estimates the added or reduced cost, applies your fee the same way the contract does, and revises the project budget. The client pays actual cost when the invoices come in, but the change order sets the expectation.
Here’s the process I’d use on every cost plus contract change:
Write the scope in plain English. What’s being added, removed, or substituted, and what it replaces.
Estimate the cost. Get sub and supplier pricing, the same way you built the original budget.
Apply the fee per the contract. Percentage, fixed fee, or a fee adjustment clause. Don’t improvise.
State the schedule impact. Days added, or “0 days.” Never blank.
Show the revised budget. Original estimate, prior changes, this change, new estimated total.
Get the signature before work starts. Email approval counts only if your contract says it does.
Tag the costs. Code every invoice for that change to its own line so you can show actual vs estimated later.
If you don’t want to build the form and the process from scratch, the Custom Home Change Order Template gives you a template plus a guide to running a simple, profitable change order system.
Cost plus change order example
Here’s a simple sample with round, hypothetical numbers. The contract is cost plus a 15 percent fee, and the client wants to add a 300-square-foot covered patio.
Change order #6: Add covered rear patio per revised sheet A-3.
Estimated cost: $30,000 (concrete, framing, roofing, electrical, paint).
Builder fee at 15 percent: $4,500.
Estimated total for this change: $34,500.
Schedule impact: 8 working days.
Revised project estimate: $850,000 original, plus $22,000 in prior changes, plus $34,500, equals $906,500.
Note: Billed at actual cost plus fee. Final cost may vary from the estimate.
That last line is the one that separates a cost plus change order from a fixed-price one. You’re approving scope and an estimate, not locking a price, unless your contract says otherwise.
Change orders on cost plus vs fixed price: what’s different?
On a fixed-price contract, the change order sets a new price, and you eat any overrun on that change. On cost plus, the change order sets a new estimate, and the client pays actual cost plus fee. The comparison comes down to who carries the risk.
Price. Fixed price: a firm number. Cost plus: an estimate plus the fee method.
Markup. Fixed price: your markup is built into the number. Cost plus: the fee follows the contract. More on pricing in change order markup.
Credits. Deleted scope on cost plus reduces cost automatically. On fixed price, you negotiate the credit.
Documentation. Both need a signed change order. Cost plus also needs clean cost coding so invoices tie back to the change.
Should the fee change on a cost plus change order?
Usually yes, and the contract should say how. If your fee is a percentage of cost, it grows with every added dollar. If it’s a fixed fee, you want a clause that adjusts it when scope changes beyond a certain size, or you end up managing a bigger house for the same money.
The worst setup is a fixed fee with no adjustment language. The client adds a guest house and you’re supervising it for free. Fix that in the contract, not in the field. The change order clause in your construction contract is where this lives.
How do you track cost plus contract changes?
Keep a change order log and code every cost to the change it belongs to. On cost plus, the client sees every invoice, so you want each one to land in the right bucket.
One line per change order. Number, date, description, estimate, fee, signed date, status.
A cost code for each change. So the patio costs don’t blend into the base house.
Estimate vs actual on each change. Review it monthly with the client.
Allowance overages too. Treat them the same way. See how construction allowances work.
A change order log takes ten minutes a week. It saves you the month-long argument at the end.
What mistakes do builders make with cost plus changes?
The big one is skipping the paperwork because the client pays cost anyway. The others follow from it.
Verbal approvals. “He said yes on site” doesn’t hold up when the invoice shows up.
No revised budget. The client keeps comparing against the original number.
Fee surprises. The client didn’t realize the fee applied to the upgrade.
Mixed cost codes. Nobody can tell what the change actually cost.
Waiting to bill. Late reconciliation turns small questions into big disputes.
When you want one system for writing, pricing, and logging every change, the Custom Home Change Order Template keeps it organized from the first change to the last.
Frequently asked questions
Can a builder charge a fee on change orders in a cost plus contract?
Usually, if the contract says the fee applies to all cost of the work, including changes. Spell it out in the contract and repeat it on each change order so there’s no surprise.
Is a cost plus contract with a guaranteed maximum price handled differently?
Yes. With a guaranteed maximum price, change orders typically adjust the cap as well as the estimate. Confirm the exact mechanics with your attorney, since contract language varies.
Do deductive changes reduce the fee on cost plus?
With a percentage fee, removing cost removes fee automatically. With a fixed fee, it depends on your contract’s adjustment clause.
What if the actual cost of a change runs over the estimate?
On a true cost plus contract, the client generally pays actual cost plus fee. Tell them early when a change is trending over, so it’s a conversation and not a surprise.
BTW, if you want every cost plus change documented, priced, and signed the same way every time, grab our Custom Home Change Order Template over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.