A fix and flip scope of work template is a room-by-room and system-by-system list of every repair and upgrade planned for a rehab, with the specific material, quantity, and cost for each item. A good one describes the work clearly enough that a contractor can bid it, a lender can fund draws against it, and you can check it off at the end. Write it after a detailed walkthrough, organize it by area or trade, and attach a budget to every line.
The scope is where flips are won or lost before anyone swings a hammer. Vague scope means vague bids, change orders you can’t argue with, and a lender who won’t release a draw because they can’t tell what’s done. Most busted flip budgets I hear about trace back to a scope that said “update kitchen” and nothing else.
What is a fix and flip scope of work?
A fix and flip scope of work is the written plan for the rehab. It lists what will be repaired, replaced, or added, where, with what materials, and what it should cost. Investors use it to estimate the rehab budget, lenders use it to approve and fund the loan, and contractors use it to bid.
It’s the same idea as a subcontractor scope on a new build, just applied to a house that already has surprises in the walls. If you’re weighing a flip against building new, see fix and flip vs new construction.
What should a rehab scope of work include?
Here’s a checklist for a complete rehab scope of work:
Property information. Address, square footage, bed and bath count, year built.
Exterior. Roof, gutters, siding, paint, windows, doors, landscaping, fencing, driveway.
Structure. Foundation repairs, framing repairs, any engineer recommendations.
Systems. Electrical panel and wiring, plumbing supply and drain, water heater, HVAC.
Kitchen. Cabinets, counters, backsplash, sink and faucet, appliances, lighting.
Bathrooms. Each one separately: tub or shower, tile, vanity, toilet, fixtures, mirror, fan.
Interior. Flooring by room, drywall repair, paint, trim, interior doors, hardware.
Permits. Which items need one. Check with the local building department.
Exclusions. What’s not included, written down.
Contingency. A separate line for what you find after demo.
How to write a fix and flip scope of work, step by step
Walk the house with a checklist. Every room, every system, attic and crawlspace too.
Get inspections where needed. Foundation, roof, sewer line, or electrical if anything looks off.
Decide the finish level. Based on comps for the after-repair value, not on taste.
List each item by area. Location, task, material, quantity.
Spec the materials. “LVP, 7-inch plank, color to match” beats “new floors.”
Price each line. From contractor bids, supplier quotes, or recent jobs. See how to estimate construction costs.
Add contingency. Rehabs hide more than new construction does.
Group into draw phases. So the lender can fund in stages. See construction draw schedules.
Send it out for bids. Same scope to every contractor.
If you want a structure that already separates budget and specs, the Construction Budget and Specifications Template gives you detailed budget and specifications templates in a simple system that adapts well to a rehab.
Fix and flip scope of work template: a sample section
Here’s a sample section for one bathroom, with hypothetical round numbers:
Hall bath, demo: Remove tub surround, vanity, toilet, flooring. $800.
Hall bath, tub: Keep existing tub, reglaze white. $500.
Hall bath, tile: 12x24 porcelain surround to ceiling, cement board and waterproofing. $2,400.
Hall bath, vanity: 36-inch vanity with top, faucet in matte black. $900.
Hall bath, toilet: New elongated toilet. $350.
Hall bath, flooring: Porcelain tile, 45 square feet. $700.
Hall bath, electrical: New vanity light and exhaust fan, GFCI outlet. $600.
Hall bath, paint and accessories: Walls, ceiling, mirror, towel bar, TP holder. $450.
Hall bath total: $6,700.
That level of detail lets three contractors bid the same bathroom. “Remodel hall bath” gets you three different bathrooms at three different prices.
How do you build a fix and flip budget spreadsheet from the scope?
Every line in the scope becomes a line in the fix and flip budget spreadsheet. Add columns for the budget, the bid, the contractor, actual cost, and status. Then add a summary at the top with the purchase price, rehab total, holding costs, selling costs, and projected profit.
Scope columns: Area, task, spec, quantity.
Money columns: Budget, awarded bid, actual, variance.
Tracking columns: Contractor, start, complete, inspected, paid.
Summary: All-in cost against after-repair value.
What mistakes do flippers make with scope of work?
Too vague. “Update kitchen” can mean anything.
Skipping systems. Pretty finishes over old wiring and plumbing come back to bite.
No contingency. Every flip finds something after demo.
Over-improving. Finishes above what the comps support.
Different scopes to different bidders. Then the bids aren’t comparable.
No exclusions. Disputes about what was included.
Ignoring permits. Requirements vary by jurisdiction; confirm with your building department.
Writing scopes for trades works the same way on new builds. See subcontractor scope of work.
Why should the scope and budget live together?
Because the scope says what and the budget says how much. When they’re separate, they drift. The contractor bids from one version, the lender funds from another, and you’re tracking a third. Keep one document.
I go deeper on pairing the two in construction budget and specifications. The Construction Budget and Specifications Template keeps budget and specs organized in one system, which is exactly what a fix and flip scope of work template needs underneath it.
Frequently asked questions
Do hard money lenders require a scope of work?
Many do, especially when they fund rehab costs in draws. Each lender has its own format, so ask for theirs before you write yours.
How much contingency should a flip budget have?
It varies with the age and condition of the house. Older homes and homes with unknown systems usually need more. Base it on what you saw in the walkthrough and inspections.
Who writes the scope of work on a flip?
Usually the investor, sometimes with the general contractor. Either way, the investor should own and approve it.
Should the scope of work include material brands?
Include enough detail to price it: type, size, and finish. Name brands where it matters, like appliances or fixtures.
BTW, if you want your rehab scope and budget in the same organized system, grab our Construction Budget and Specifications Template over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.