General conditions in construction are the job-specific costs of running the project that don’t belong to any single trade: supervision, temporary utilities, dumpsters, portable toilets, cleaning, job site protection, equipment rental, and similar items. In the construction budget, general conditions get their own group of line items so they’re visible, priced, and tracked like everything else. They are not the same as company overhead, which covers the costs of running your business across all jobs.
General conditions are where a lot of builders quietly give away margin. They estimate the trades carefully, then guess at the dumpsters and the superintendent’s time. A job that runs two months long burns general conditions every single week, and if they weren’t budgeted right, that money comes straight out of your fee.
What are general conditions in construction?
General conditions are the costs of keeping a specific job site running for the length of the project. If the cost exists because this job exists, and it doesn’t belong to one trade, it’s usually a general condition.
You’ll also see the term used for the general conditions section of a contract, which is the legal boilerplate about responsibilities, insurance, and disputes. Same name, different thing. This article is about the budget side. On commercial specs, the same costs are often organized under “general requirements,” which is Division 01 in the standard spec format.
What should construction budget general conditions include?
Here’s a checklist of the construction budget general conditions I’d price on a typical home. Not every job needs every line.
Supervision. Superintendent or project manager time charged to the job, if your contract allows it.
Temporary power. Pole, setup, and monthly bills.
Temporary water. Meter, hookup, and usage.
Portable toilet. Rental and service for the full schedule.
Dumpsters. Delivery, pulls, and overage fees.
Job site cleaning. Ongoing cleanup, rough clean, final clean.
Erosion control and site protection. Silt fence, rock entrance, tree protection.
Equipment rental. Lifts, forklifts, scaffolding not covered by a sub.
Job signage and fencing. Where required.
Builder’s risk insurance. Confirm requirements with your insurance agent.
Floor and finish protection. Paper, board, door covers.
Small tools and consumables. If you charge them to jobs.
If you want a head start on the full structure, the Construction Budget and Specifications Template gives you detailed budget and specifications templates in one simple system.
How do you calculate general conditions cost?
Most general conditions are time-based, so you calculate them as a monthly or weekly rate times the schedule. The rest are one-time setup costs. Get the schedule right first, then price the general conditions from it.
Set the schedule. How many months from start to final clean.
List time-based items. Supervision, power, water, toilet, equipment.
Price each per month. Use real bills from past jobs, not memory.
Multiply by the schedule. Add a small buffer for slippage.
Add one-time items. Setup fees, signage, erosion control, final clean.
Add count-based items. Dumpster pulls, cleanings.
Review against history. Compare to what similar jobs actually spent.
General conditions cost example
Here’s a simple worked example for a hypothetical home with an eight-month schedule. Numbers are round and for format only; your market will differ.
Supervision: $3,000 per month times 8 = $24,000.
Temporary power: $600 setup plus $150 per month times 8 = $1,800.
Portable toilet: $175 per month times 8 = $1,400.
Dumpsters: 7 pulls at $550 = $3,850.
Cleaning: rough, final, and windows = $2,500.
Erosion control and signage: $1,500.
Total general conditions: $35,050.
Now stretch that schedule to ten months. Supervision, power, and the toilet alone add about $6,650. That’s the real cost of a slow job, and it’s why I care so much about the schedule.
General conditions vs overhead: what’s the difference?
General conditions are tied to one job. Overhead is the cost of running the company: office rent, accounting, software, admin salaries, marketing. If the cost would exist with zero active jobs, it’s overhead.
General conditions: charged to the specific project, usually shown in the budget.
Overhead: covered by your fee or markup, spread across all jobs.
The line gets blurry with supervision. Some builders charge superintendent time as a general condition, some cover it in the fee. On cost plus jobs, the contract should say which. If it doesn’t, you’ll argue about it. More on contract types in cost plus vs fixed price.
What are common general conditions mistakes?
The common ones come from estimating general conditions as a guess instead of a calculation.
Using a flat percentage. It hides the link to the schedule.
Forgetting the monthly bills. The setup fee is in, the usage isn’t.
Underestimating dumpsters. Framing and drywall fill them fast.
Not budgeting supervision honestly. Your superintendent’s time is real cost. See superintendent vs project manager for how the roles split.
Burying them in trade lines. Then you can’t track them.
No schedule buffer. Jobs rarely finish early.
Where do general conditions go in the budget?
Treat general conditions in construction like any other trade. Put them near the top, right after soft costs, as their own group with their own cost codes. That way they show up on every draw request and every budget vs actual report, and nobody can miss them.
I list every line I use in construction budget line items, and construction budget and specifications covers how the budget and spec sheet work together.
The Construction Budget and Specifications Template keeps general conditions, trade lines, and specs organized in the same system, so nothing falls between them.
Frequently asked questions
What percentage of a construction budget is general conditions?
It varies a lot by project size, schedule, and how you charge supervision. Calculate it from your schedule and past jobs instead of using a fixed percentage.
Are general conditions part of the contractor’s fee?
Usually not. General conditions are typically a cost of the work, while the fee covers overhead and profit. Your contract should define it clearly.
Is builder’s risk insurance a general condition?
Many builders carry it as a general condition, though some put it under soft costs. Confirm coverage needs with your insurance agent.
What are general requirements in construction specifications?
General requirements are the Division 01 section of a spec, covering administrative and temporary items for the project. They line up closely with general conditions in the budget.
BTW, if you want general conditions priced and tracked in the same place as the rest of the job, grab our Construction Budget and Specifications Template over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.