Owner furnished, contractor installed (OFCI) means the client buys a product and the builder or a subcontractor installs it. On a custom home, OFCI items are usually things like light fixtures, plumbing fixtures, appliances, hardware, or tile the homeowner wants to source themselves. The builder’s job is to set clear rules up front: what can be owner-supplied, when it must arrive, who inspects it, who carries the risk if it’s wrong or damaged, and how warranty and installation pricing work.
OFCI sounds simple until the wrong faucet shows up the day before trim, or a box of tile is three cartons short, or a chandelier arrives cracked and nobody knows whose problem it is. Without written rules, owner furnished materials turn into schedule delays, finger-pointing, and warranty calls you didn’t price. With rules, they’re just another line on the spec.
What does owner furnished, contractor installed mean?
It means the owner furnishes, or supplies, the item, and the contractor installs it. The owner pays the supplier directly. The builder doesn’t buy the product, doesn’t mark it up, and usually doesn’t warranty the product itself, though the builder may still be responsible for the installation. How that responsibility splits should be in your contract.
You’ll also see related terms on OFCI construction documents:
CFCI. Contractor furnished, contractor installed. The default for most items.
OFOI. Owner furnished, owner installed. The owner handles both.
CFOI. Contractor furnished, owner installed. Less common on homes.
Why do clients want homeowner supplied materials?
Usually to save money or to get a specific product. Some clients find a deal online, some have a family member in the business, and some just want a light fixture nobody else carries.
That’s fair. But it shifts work and risk. You lose the markup or fee on the product, you still carry the schedule, and you may get blamed for a product you didn’t choose or buy. Most builders I talk to allow some OFCI items and limit others.
What rules should builders set for owner furnished materials?
Here’s the OFCI checklist I’d put in writing before the first item shows up:
Allowed items list. Which categories can be owner-supplied and which can’t.
Deadlines. Items must be on site by a set date before installation.
Specifications. The owner provides model numbers, cut sheets, and install instructions in advance.
Inspection on delivery. Who opens and checks the item, and when.
Damage and defects. The owner handles returns and replacements with their supplier.
Quantities and overage. The owner orders enough, including waste and attic stock.
Installation pricing. Labor-only price, plus a handling or coordination fee if you charge one.
Warranty. Product warranty goes through the owner’s supplier; installation warranty as stated in your contract.
Schedule impact. Late or wrong items may delay the job, documented through a change order.
Storage and insurance. Who’s responsible for items stored on site. Check with your insurance agent.
How to handle an OFCI item, step by step
Agree in writing. Mark the item as OFCI on the spec sheet and selection sheet.
Remove it from the budget. Credit the material and any allowance; keep install labor.
Get the specs early. Model numbers and install requirements before rough-in.
Set a delivery date. With a buffer before the install date.
Inspect on arrival. Owner present or documented by photos.
Install per manufacturer instructions. And note anything unusual.
Document problems. Wrong, damaged, or short items go back to the owner in writing.
Use change orders for delays or extra labor. Same as any other change.
OFCI items need to be tracked like everything else. The Construction Budget and Specifications Template gives you detailed budget and specifications templates in a simple system, so you can mark owner-supplied items and credit them cleanly.
OFCI budget example
Here’s a simple hypothetical with round numbers. The client wants to buy their own light fixtures:
Original lighting allowance: $12,000 material.
Credit to client: $12,000 material removed from contract.
Builder fee on that material: removed with it, if your fee is percentage-based.
Installation labor: stays in the electrical contract.
Coordination fee: $750 for receiving, staging, and handling, if your contract allows it.
Net change: $11,250 credit, plus any fee credit, documented on a change order.
Delivery deadline: All fixtures on site two weeks before electrical trim.
Write it like that and nobody is confused at trim-out.
What items should not be owner furnished?
Be careful with anything that affects structure, waterproofing, code compliance, or the critical path. Common limits include:
Windows and exterior doors. Water intrusion risk and code requirements.
Roofing and waterproofing materials. Warranty and leak liability.
HVAC equipment. Sizing and installer warranty issues.
Structural components. Engineering and inspection requirements.
Anything with a long lead time on the critical path. One late item stops the job.
Some subs won’t install owner-supplied products at all, or won’t warranty the installation. Ask them before you agree.
How do you put OFCI rules in your contract?
Put an OFCI clause in your contract and summarize it in your client policies. The clause should cover approved items, deadlines, risk, warranty, and pricing. Have your attorney draft or review it, since liability and warranty rules vary by state.
Client policies like this make builds smoother. See four client policies for smoother builds, and for how OFCI items interact with allowances, see construction allowances. Warranty questions tie into your builder warranty.
The Construction Budget and Specifications Template keeps budget lines and specs organized in one place, which makes owner furnished, contractor installed items easy to mark, credit, and track. For how the budget and spec sheet fit together, see construction budget and specifications.
Frequently asked questions
Can a builder charge a fee for owner supplied materials?
Many builders charge a coordination or handling fee for receiving, storing, and managing owner-supplied items. State it in your contract up front.
Who warranties owner furnished items?
Typically the owner’s supplier or the manufacturer warranties the product, and the builder warranties the installation as defined in the contract. Confirm the language with your attorney.
Does the builder have to install whatever the owner buys?
Not if the contract says otherwise. Many builders reserve the right to refuse items that don’t meet code, specs, or installation requirements.
Are OFCI items included in the construction loan?
Often not, since the owner pays the supplier directly. Ask your client to check with their lender, especially on large items.
BTW, if you want owner-supplied items marked and credited cleanly in your budget and specs, grab our Construction Budget and Specifications Template over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.