A blower door test on new construction measures how airtight the house is. A technician mounts a powerful fan in an exterior door frame, depressurizes the house, and measures how much air leaks in through gaps in the walls, ceiling, windows, and penetrations. The result tells you how well the house was sealed, and in many areas it’s required to meet the local energy code before the home can be finished.
Why should you care? Air leaks are the energy bill you pay every month for as long as you own the house. They also bring in dust, humidity, and drafts, and they’re hard and expensive to fix once drywall and trim are up. A blower door test is one of the few quality checks that gives you an actual number instead of an opinion.
What does a blower door test on new construction measure?
It measures air leakage, the uncontrolled air moving through the building envelope. The fan pulls air out of the house to create a set pressure difference with the outside, and the equipment measures how much airflow it takes to hold that pressure. The leakier the house, the harder the fan has to work.
Results are commonly reported as air changes per hour at 50 pascals, written ACH50, which is how many times the volume of air in the house would be replaced in an hour at that test pressure. Lower is tighter. Some reports also give leakage in cubic feet per minute, or CFM50.
Is a blower door test required for a new home?
In many jurisdictions it is, as part of the energy code. In others it isn’t required but builders do it anyway, and some green building or efficiency programs require it. Whether it’s required, when it has to happen, and what result you need all vary by state and local code. Ask your builder or local building department what applies to your house.
Even where it’s not required, an air leakage test on a new home is a smart quality check. You’re spending a lot of money on insulation and HVAC. The blower door test tells you whether the envelope is holding up its end.
How does a blower door test work, step by step?
Here’s what usually happens on test day:
The house is prepped. Exterior doors and windows closed, interior doors open, fireplace dampers shut, exhaust fans off, and certain intentional openings temporarily sealed.
The fan is set up. A frame and fabric panel go into an exterior door opening with the fan mounted in it.
The house is depressurized. The fan pulls air out until the target pressure is reached.
Readings are taken. The gauge records airflow at the set pressure, often at several points.
Leaks are located. While the house is under pressure, the tester can walk around with a smoke pencil or infrared camera to find leaks.
The report is produced. Results, house volume, and whether it meets the target.
It typically takes an hour or two, depending on the house and how much leak hunting is done.
Testing is one of many quality checkpoints. Our Home Construction Checklist (Homeowner Edition) walks you through what to ask for and check in each phase, so steps like this don’t get skipped.
When should a blower door test happen?
There are two useful times:
Before drywall, as a pre-test. Some builders test once the house is dried in, insulated or air sealed, and before drywall. Leaks are easy to find and fix while the framing is still open.
At the end, as the final test. After everything is installed, this is usually the one used for code compliance or a home energy rating.
A pre-drywall test isn’t always done, but it’s worth asking about. It pairs well with your pre-drywall walkthrough.
How do you read blower door test results?
Your blower door test results will usually include the ACH50 or CFM50 number, the house volume, the target required by your code or program, and whether the house passed. Here’s a sample line from a hypothetical report:
House volume. 24,000 cubic feet
Measured leakage. 1,200 CFM50
Calculated ACH50. 1,200 times 60, divided by 24,000, equals 3.0
Target. Whatever your local code or program requires
Result. Pass or fail against that target
If it fails, the builder finds and seals the leaks and the house is retested. Common culprits include attic hatches, recessed lights, plumbing and wiring penetrations, rim joists, and gaps around windows and doors.
How does it relate to a home energy rating?
A home energy rating is a broader score of how efficient the whole house is, looking at insulation, windows, HVAC, water heating, and air leakage. The blower door test is one input. Some areas use a rating as a path to code compliance, and some builders provide one as a selling point. Ask your builder whether your home will get one, and who performs it.
What should homeowners ask the builder?
Is a blower door test required here? And what result is needed?
Who does the test? A third-party rater or the builder’s own team?
Will there be a pre-drywall test?
How is air sealing done? What materials and which areas?
Can I get a copy of the report? Keep it with your closing documents.
Does ventilation match the tightness? A tight house needs a plan for fresh air, and your HVAC contractor should have one.
For more questions like these, see questions to ask during construction and how to check builder quality.
A blower door test on new construction gives you one clear number about how the house was built. The Home Construction Checklist (Homeowner Edition) keeps that and every other checkpoint in one place, phase by phase.
Frequently asked questions
How much does a blower door test cost?
It varies by market and by who performs it. On most new homes it’s part of the builder’s cost, so ask whether it’s included in your contract.
Can a house be too airtight?
A tight house is good, but it needs mechanical ventilation to bring in fresh air and control humidity. Ask your builder how ventilation is designed for your house.
What happens if my house fails the blower door test?
The builder finds and seals the leaks, then the house is retested. It can delay the final inspection, which is one reason some builders test before drywall.
Do I need to be there for the blower door test?
No, but it’s interesting to watch if you can. Ask your builder whether you can be on site and see the leak search.
BTW, if you want every quality checkpoint in your build mapped out by phase, grab our Home Construction Checklist (Homeowner Edition) over at the Building Optimal Shop. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.