A time and materials contract is an agreement where the client pays for the actual labor hours at set rates, plus the actual cost of materials, usually with a markup on both. It makes sense in construction when the scope can’t be defined well enough to price up front: remodels with unknown conditions, repairs, small add-on work, and changes in progress. It makes less sense on a new home with complete plans, where a fixed price or cost-plus contract gives the client more certainty.
T&M has a reputation as a blank check. It doesn’t have to be one. Done with clear rates, daily records, and a cap or a checkpoint, it’s one of the fairest ways to price work nobody can see yet. Done loosely, it’s a dispute with a start date.
What is a T&M contract in construction?
A T&M contract in construction usually has four parts:
Labor rates. An hourly rate for each type of worker, like a lead carpenter, helper, or superintendent.
Materials at cost. Actual invoiced cost of materials, supported by receipts.
Markup. A percentage on materials, and sometimes on subcontracted work, to cover overhead and profit.
Equipment and other costs. Rental equipment, dumpsters, permits, and similar items, either at cost or at set rates.
Some T&M contracts also include a not-to-exceed amount, which caps the total unless the client approves more. Have your attorney review whatever structure you use, since contract rules vary by state.
When does a time and materials contract make sense?
A time and materials contract makes sense when the work is real but the scope is unknowable until you open things up. Common examples:
Remodel demolition and discovery. You don’t know what’s behind the wall.
Repair work. Water damage, rot, and structural fixes.
Small add-ons where writing a detailed bid costs more than the work.
Change work in progress when the client needs a decision faster than you can price it, and your contract allows T&M changes.
Warranty work outside coverage that the client wants you to handle.
On a new home, I’d keep T&M to narrow situations like these. If you’re choosing a contract model for the whole house, see cost-plus vs. fixed price.
Time and materials vs fixed price: which is better?
Neither is better in general. Time and materials vs fixed price is a question of who carries the risk of the unknown.
Fixed price. The builder carries the risk. If it takes longer or costs more, that’s the builder’s problem. Best when the scope is well defined.
Time and materials. The client carries the risk. If it takes longer, they pay more. Best when the scope is genuinely unknown.
Cost-plus with a budget. Somewhere in between. Common on custom homes.
A hypothetical: say a client wants a rotted subfloor repaired under a bathroom. You won’t know how far it goes until the tile is up. A fixed price means padding for the worst case. T&M with a not-to-exceed of, say, $5,000 and a checkpoint at $3,000 lets you bill what it actually takes, and gives the client a ceiling.
How should you handle time and materials pricing?
Time and materials pricing has to be clear before work starts, and documented while it happens. Here’s what I’d put in place:
Set the rates in writing. Hourly rates by role, markup percentages, and what’s billed at cost.
Define what a billable hour is. Travel time, supply runs, and minimum charges should all be stated.
Keep daily logs. Who worked, how long, and on what. Photos help.
Keep every receipt. Materials billed at cost need backup.
Bill frequently. Weekly or at short intervals, so the client never gets a surprise.
Set a cap or checkpoint. A not-to-exceed amount, or a point where you stop and get approval to continue.
Get signatures. Have the client or their representative sign daily tickets if possible.
Your markup logic should match the rest of your business. See change order markup and builder markup vs. margin.
How does T&M work for change orders?
Sometimes a change can’t be priced up front, and you still need to move. A T&M change order handles that. Instead of a fixed price, the change order states the scope, the rates, a not-to-exceed amount, and how the final number will be documented. The client signs that before the work starts, and you bill the actual cost when it’s done.
It still needs paperwork. A T&M change with no signature is just an argument you haven’t had yet. Our Custom Home Change Order Template gives you a change order system you can use for both fixed-price and T&M changes. More on the basics in how to write a construction change order.
What are the risks of time and materials work?
For the builder, the main risk is collection. Clients who agreed to T&M sometimes balk when they see the hours. For the client, the main risk is open-ended cost. Both risks shrink with the same habits:
Clear rates agreed in writing.
Daily documentation the client can see.
Frequent billing so totals never jump.
A cap or checkpoint to keep the scope from drifting.
Frequently asked questions
Is a time and materials contract legal for residential work?
Generally yes, but some states have specific requirements for residential contracts. Have your attorney review your contract before using it.
What is a not-to-exceed amount?
A cap on the total price under a T&M arrangement. The builder can’t bill beyond it without the client’s written approval.
Do I mark up materials on a T&M contract?
Most builders do, to cover overhead and profit. State the markup clearly in the contract.
How do I prove hours on a T&M job?
Daily logs, photos, and signed tickets. The more the client sees during the job, the fewer questions at the end.
BTW, if you want T&M changes documented and signed the same way as every other change, grab our Custom Home Change Order Template over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.