Loan to cost vs loan to value is the difference between sizing a construction loan on what the project costs and sizing it on what the finished property is worth. Loan to cost (LTC) is the loan divided by total project cost. Loan to value (LTV) is the loan divided by the appraised value. Most construction lenders check both and lend the lower amount, and your equity covers the gap.
This matters because the gap is your cash. If you plan the deal on one number and the lender sizes it on the other, you find out at closing that you need to bring tens of thousands more. That’s a bad day to discover it.
What is loan to cost in construction?
Loan to cost construction math is simple: loan amount divided by total project cost. Total cost usually means land, hard costs, and soft costs, and sometimes financing costs and an interest reserve, depending on the lender.
LTC = Loan amount / Total project cost
If your project costs $500,000 and the lender offers 80% LTC, the most they’ll lend on cost is $400,000. You bring $100,000.
Lenders like LTC because it measures how much of your own money is at risk. More skin in the game, less risk for them.
What is construction loan LTV?
Construction loan LTV is loan amount divided by the property’s value, usually the appraised as completed value for new construction.
LTV = Loan amount / Appraised value
If the as completed value is $650,000 and the lender offers 70% LTV, the most they’ll lend on value is $455,000.
LTV protects the lender if they have to take the property back and sell it. If values drop, there’s still a cushion. For how that value gets set, read how lenders appraise a spec home.
LTC vs LTV: which one limits your loan?
On LTC vs LTV, the lower result usually wins. Lenders calculate both caps and lend the smaller one.
LTC limits the loan when your costs are high relative to value. Thin-margin deals hit this cap.
LTV limits the loan when the value is low relative to costs, or the lender’s LTV percentage is low. Low appraisals hit this cap.
Good deals usually have a value well above cost, so LTC sets the loan and the LTV has room to spare.
Lenders may also use a third test, loan to land value or a maximum loan amount. Ask what applies.
How do you calculate loan to cost vs loan to value step by step?
Here’s the order I’d run before talking to a lender.
Total your project cost. Land, hard costs, soft costs, and the financing costs your lender includes.
Estimate the as completed value. From recent comparable new construction sales.
Get the lender’s percentages. Their maximum LTC and LTV for your experience and deal type.
Calculate the LTC cap. Cost times max LTC.
Calculate the LTV cap. Value times max LTV.
Take the lower number. That’s your likely loan.
Subtract from total cost. That’s your required equity.
Stress test. Rerun with a lower appraisal and a cost overrun.
Steps one and two come straight from your pro forma, and the Spec Home Pro Forma Template gives you a quick yes or no with those numbers on one page you can share with banks.
Example: LTC and LTV on one spec home
Hypothetical round numbers, with a lender at 80% LTC and 75% LTV.
Total project cost: $550,000
As completed value: $680,000
LTC cap: 80% of $550,000 = $440,000
LTV cap: 75% of $680,000 = $510,000
Loan: $440,000 (LTC wins)
Equity required: $110,000
Now say the appraisal comes in at $570,000. The LTV cap drops to $427,500, and that becomes your loan. Equity goes to $122,500, and your margin just told you something too. These are illustrative numbers. Actual ratios vary widely by lender, market, and borrower.
What counts as project cost for LTC?
It depends on the lender, which is why you should ask early. Common inclusions:
Land. Purchase price, or sometimes appraised value if you already own it.
Hard costs. The construction budget.
Soft costs. Plans, engineering, permits, insurance, and fees.
Financing costs. Loan fees and sometimes an interest reserve.
Contingency. Often required as a line in the budget.
Some lenders exclude your developer fee or overhead from cost. If you own the land free and clear, some lenders count its value as part of your equity. Ask each lender how they treat land and fees. See construction loan equity requirements for more.
Common mistakes with LTC and LTV
Planning on LTV alone. Assuming the loan will be a percentage of value when LTC is lower.
Optimistic value. Using a sale price the appraisal won’t support.
Leaving out soft costs. Understating total cost, then coming up short.
Not asking what counts. Lenders define cost differently.
No cushion. Overruns come out of your pocket, not the loan.
How do you plan equity around both ratios?
Run loan to cost vs loan to value on every deal before you sign the land contract, and plan your equity on the lower loan with a cushion. Keep your cost and value assumptions in one consistent pro forma so the lender sees the same numbers you used to decide. The Spec Home Pro Forma Template keeps that page clean from deal to deal. For financing options, read spec home financing.
Frequently asked questions
Is LTC or LTV more important for construction loans?
Both matter, and lenders usually lend the lower of the two. On most new construction deals with healthy margins, LTC is the tighter limit.
What is a typical loan to cost for a spec home?
It varies by lender, market, and your experience. Ask several lenders, and expect newer builders to get lower ratios than experienced ones.
Does LTV use the current value or the finished value?
For construction loans, lenders usually use the as completed value from the appraisal. Some also look at the as is land value at closing.
Can land equity count toward the loan to cost?
Many lenders will credit land you own toward your equity, based on purchase price or appraised value. Policies differ, so confirm with your lender.
BTW, if you want your cost and value numbers on one page before a lender sizes the loan, grab our Spec Home Pro Forma Template over at the Building Optimal Shop, where you can check out the rest of our swag to build a better business. Proceeds go to benefit, Exponencialistas, my non-profit investing in entrepreneurs transforming their communities in Latin America.